Home
| Databases
| WorldLII
| Search
| Feedback
Supreme Court of Papua New Guinea |
PAPUA NEW GUINEA
IN THE SUPREME COURT OF JUSTICE
SCA 40 OF 2010
BETWEEN:
RAMU NICO MANAGEMENT (MCC) LIMITED
First Appellant
AND:
MINERAL RESOURCES AUTHORITY
Second Appellant
AND:
DR WARI IAMO
in his capacity as the Director of the Environment
Third Appellant
AND:
DEPARTMENT OF ENVIRONMENT AND CONSERVATION
Fourth Appellant
AND:
THE INDEPENDENT STATE OF PAPUA NEW GUINEA
Fifth Appellant
AND:
EDDIE TARSIE
for himself and in his capacity as Ward Councillor of Ward 3, Sidor LLG
First Respondent
AND:
FARINA SIGA
for himself and in his capacity as Ward Secretary of Ward 3, Sidor, LLG
Second Respondent
AND:
PETER SEL
Third Respondent
AND:
POMMERN INCORPORATED LAND GROUP NO 12591
Fourth Respondent
AND:
SAMA MELAMBO
for himself and as Chairman of Pommern Incorporated Land Group
Fifth Respondent
Waigani: Davani, Hartshorn and Sawong JJ.
2010: 2nd, 16th July
APPEAL against exercise of discretion, principles to disturb - Standing to sue
ENVIRONMENT ACT 2000 ss 136(1) & 136(3) – whether environmental approval lawful –interpretation - - Regulation - gazettal notice, whether adequate notice to villagers –
PUBLIC OR PRIVATE NUISANCE– whether action for law of Papua New Guinea – defence of statutory authority to action for nuisance –
UNDERTAKING AS TO DAMAGES (value thereof)
NATIONAL GOALS AND DIRECTIVE PRINCIPLES, whether give rise to serious issue to be tried -
INJUNCTIVE ORDERS – arguable case – balance of convenience - delay
Facts
The appellants are the owner of a nickel mine in Madang Province now under construction and due for completion this year 2010. The other appellants are the State and the State regulatory bodies concerned with the construction and operation of the mine. The Respondents claim to be landowners affected by the proposed activities of the first appellant. Pursuant to legislation now repealed the first appellant obtained approval of the Ramu Nickel Environmental Plan 1999. The repealed legislation was replaced by the Environmental Act 2000 which contained a saving provision for approvals granted prior to that Act coming into force. The Ramu Nickel Environmental Plan 1999 provides for approximately 100,000,000 tonnes of tailings waste plus other waste material to be deposited into Basamuk and Astrolabe Bays over the life of the mine. In the National Court the Respondents obtained an interim injunction preventing construction of any undersea part of the tailings disposal system, arguing that (1) the activity proposed by the Ramu Nickel Environmental Plan 1999 is unlawful, the approval of the Plan is unlawful, and (2) because the mine was not operating on the coming into force of the Environmental Act 2000 the Ramu Nickel Environment Plan 1999 was not saved by the saving provision in s136(3) of the Act and the proposed undersea tailings disposal is unlawful under the Environmental Act 2000.
Held:
Davani and Sawong JJ, (Hartshorn J dissenting):
1. The Respondents are entitled to bring the proceedings for themselves, they do not necessarily represent other landowners at [10]. The trial judge did not err in finding the Respondents had standing; per Davani J at [11];
2. Serious questions are raised in relation to the law of nuisance & whether serious environmental damage will be caused; Davani J at [21]; If the undersea tailings disposal is allowed to proceed the potential environmental harm far outweighs the lifting of the injunction; Sawong J at [128];
3. The Appellants submission that the trial judge misinterpreted s136(3) of the Environment Act must be argued after defences are filed and evidence is tested; Davani J at [31];
4. An appellate court will be very cautious in reviewing interlocutory decisions; Davani J at [38];
5. The trial judge did not exercise his decision upon a wrong principle, take extraneous or irrelevant matters into account, mistake the facts or not take some matter into consideration; Davani J at [40]-[41];
6. The very serious issues raised relating to possible environmental damage are exceptional, the balance of convenience lies in maintaining the injunction and for the issues to go to trial; Davani J at [46]; . One of the key issues is whether the environmental harm that is likely to occur once the pipe line is constructed and the tailings are discharged, is authorized; per Sawong J at [118]; The Court should not brush aside the concerns of the landowners on a narrow basis; Sawong J at [125];
7.The principles upon which a court may grant an interlocutory injunction are well-established, namely, whether there is a serious question to be tried (Hartshorn J concurring at [53]), and discretionary matters such as where the balance of convenience lies and delay, and the provision of an appropriate undertaking as to damages; Sawong at [90] Davani J concurring at [1];
8. The consideration or application of the National Goals and Directive Principles in the Constitution is a serious issue to be tried; Sawong at [121];
9. Whether the common law principles relating to the statutory defence (to the common law action for nuisance) is or are appropriate and applicable to the circumstances of this case in particular and circumstances of PNG in general, is a serious issue to be tried; Davani J at [21], Sawong J at [124];
10. Per Davani and Sawong JJ the appeal is dismissed;
11. Per Hartshorn J (dissenting) [56] A serious question to be tried is not an arguable case that cannot be described as a strong case and which does not have a real possibility of ultimate success; at [61] There is no serious question to be tried, the appellants operated under approvals given under statute; the interpretation of s136(3) of the Environment Act as contended by the respondents is wrong and has no application to the facts, s136(1) is the principle saving provision; the evidence and arguments before the primary judge did not give rise to a serious as opposed to a speculative case; at [71] the lack of evidence of the first appellant's behavior did not entitle the primary judge to find that there was a serious case that the anticipated environmental damage was not an inevitable consequence of the approved plan, thus not giving rise to a statutory defence to a claim in nuisance.
DECISION
Cases Cited
Papua New Guinea Cases
Ariako v Madang Provincial Government [1995] PNGLR 38
Avia Aihi v State [1982] PNGLR 92
Chief Collector of Taxes v. Bougainville Copper Ltd (2007) SC853
Sir Julius Chan v The Ombudsman Commission of Papua New Guinea [1999] PNGLR 240
Craftworks Nuigini Pty Ltd v. Allan Mott (1997) SC525
Curtain Bros (PNG) Ltd v. UPNG (2005) SC788
Ewasse Landowners Association Incorporated v. Hargy Oil Palms Limited (2005) N2878
Gideon Barereba v. Margaret Elias (2002) N2197
Gobe Hongu Limited v. The National Executive Council & Ors (1999) N1920
Golobadana No.35 Ltd v. Bank of South Pacific Ltd (2002) N2309
Grand Chief Sir Michael Somare v. Ila Geno & Ors (2008) N3406
Kuluah v University of PNG [1993] PNGLR 494
Markscal Limited v Mineral Resource Development Co. Pty Ltd [1996] PNGLR 419
MAS International Ltd v. David Sode (2008) SC944
Moresby North East election Petition, Paterson Lowa v Goasa Damena [1977] PNGLR 429
Ron Napitalai v. PNG Ports Corporation Ltd & Ors (2010) SC1016
New Britain Oil Palm Ltd v. Vitus Sukuramu (2008) SC946
NHC v. Yama Security Services Pty Ltd [2000] PNGLR 69
PNG v Albert [1988] PNGLR 138
Pacific Equities and Investment Ltd v. Melanesian Trustee Services Ltd(2007) N3122
Public Employees Association v Liosi [1988-89] PNGLR 585
Robinson v National Airlines Commission [1983] PNGLR 478
Jerry Singirok v. NEC & Ors (1977) N1590
State v. Sam Akoita & Ors (2009) SC977
Stettin Bay Lumber Company Pty Ltd v Arya Ship Management Ltd (1995) SC488
Southern Highlands Provincial Government v. NHC (2001) N2110
The Government of Papua New Guinea and Richard Harold Davis v Stanley Barker [1977] PNGLR 386 SC123
Overseas Cases
American Cyanide Company v. Ethicon Limited (1975) 1 All ER 594
Caledonian Railway Co. v. North British Railway Co (1881) 6 App cases 114
Marriage v East Norfolk Rivers Catchment Board [1949] 2 All ER 1021
Will of Gilbert 1946 (NSW) LR 318
Counsel:
Mr. C. Scerri Q. C. and Mr. G. Gileng, for the First Appellant
Mr. G. M. Egan and Mr. A. Mana, for the Second Appellant
Mr. I. R. Molloy and Mr. W. Mapiso, for the Third, Fourth and Fifth Appellants
Mrs. T. G. Nonggorr and Mr. R. William, for the Respondents
16th July, 2010
The Writ of Summons and Statement of Claim
"3. In or around January 1999 Ranu Nickel Ltd lodged an application for a Special Mining lease for the Ramu Nickel project and lodged the Ramu Nickel Environmental Plan 1999 for this project with the Fourth Defendant.
3A. On 21 March 2000 the Department of Environment and Conservation approved the Ramu Nickel Environmental Plan 1999 under the repealed legislation the Environmental Planning Act (repealed).
4. On 26 July 2000 the Special Mining Lessee (hereinafter referred to as "SML") was granted to Ramu Nickel Ltd.
5. The SML was subject to numerous conditions including that the lessee shall comply with all the relevant legislation applicable to the lease including that administered by the department of Mining, Office of Environment and Conservation and the Bureau of Water Resources.
6. On 1 January 2004, the Environment Act 2000 came into force and amongst other things repealed the Environmental Planning Act, the Water Resources Act and the Environmental Contaminants Act.
7. The Ramu Nickel Environmental Plan 1999 Approval was saved however pursuant to section 136 of the Environment Act 2000.
8. In 2004 however the China Metallurgical Construction Company (hereinafter referred to as "MCC"), a Chinese State-owned steel company started negotiations to fully finance the operations, including rights to construct, operate and secure off take arrangements for the proposed Ramu Nickel mine.
9. On 9 February 2004 a framework agreement was signed in Beijing by MCC, Ramu Nickel Limited, Mineral Resources Development Company Limited and the Independent State of Papua New Guinea. The Plaintiffs, nor any landowners were consulted nor involved. The framework agreement state that those parties agree in good faith to form a Joint Venture to develop the project and that the "landowners" would be a party to the Joint Venture. The agreement records that Ramu Nickel Limited and the State shall give the mine and all exploitation rights to MCC in exchange for only a 15% interest and that MCC would be responsible for the 100% funding of the project.
10. A Joint Venture Agreement and also a Mining Development contract were signed between MCC, Ramu Nickel Limited and the Independent State of Papua New Guinea in 2005 and the SML was transferred from Ramu Nickel Limited to MCC.
11. A company was registered by its 100% owner MCC to manage and operate the Ramu Nickel mine project and that is the First Defendant.
12. The construction of the mine commenced in 2008 by the First Defendant, but the mine is not yet operational.
13. When operational, the Ramu Nickel mine will be a series of open cut mine pits and a beneficiation plant to produce ore slurry at Kurumbrukari in Madang Province. A slurry pipeline approximately 134km long will transport the ore slurry from the Kurubukari mine site eastwards to the refinery plant at Basamuk Bay on the Rai Coast. The refinery plant will produce nickel metal and a cobalt salt product using acid pressure leaching technology.
14. The Ramu Nickel Environmental Plan 1999 was prepared by NSR Environment Consultants Pty Ltd, an Australian company that has advised companies on 25 ocean disposal projects clustered in 9 countries being Indonesia, Papua New Guinea, New Caledonia, the Philippines, Chile, Fiji, the Solomon Islands, Cuba and Canada.
15. According to the Ramu Nickel Environmental Plan 1999 Approval, the First Defendant will then dump 5 million tones of hot tailings into Astrolabe Bay each year for the life of the mine which is estimated at 20 years, totaling 100 million tones of tailings. The First Defendant will additionally dump waste rock and soil directly into the sea at Basamuk Bay during the construction and life of the mine as well as sewerage from 2500 people for 30 months.
16. This activity of disposing tailings and waste into Basamuk and Astrolabe Bay by the First Defendant and consequently the Ramu Nickel Environmental Plan 1999 Approval will adversely affect matters of national importance within the meaning of the Environment Act 2000, being that these activities will adversely affect:-
(a) The preservation of Papua New Guinea traditional social structures; and
(b) The maintenance of sources of clean water and subsistence food sources to enable those Papua New Guineans who depend upon them to maintain their traditional lifestyles; and
(c) The protection of areas of significant biological diversity and the habitats of rare, unique or endangered species; and
(d) The recognition of the role of land-owners in decision-making about the development of the resources on their land; and
(e) Responsible and sustainable economic development.
17. This disposal of waste by the First Defendant into Basamuk and Astrolabe Bays and consequently the Ramu Nickel Environmental Plan 1999 Approval does not protect the environment from harm and is likely to cause Environmental and or serious environmental harm.
18. This disposal of waste by the First Defendant into Basamuk and Astrolabe Bays and consequently the Ramu Nickel Environmental Plan 1999 Approval will adversely affect the beneficial value of the environment within the meaning of the Environment Act 2000 and will be detrimental to ecological health, public benefit, welfare, safety, health and aesthetic enjoyment and which requires protection from environmental harm.
19. This disposal of waste by the First Defendant into Basamuk and Astrolabe Bays and consequently the Ramu Nickel Environmental Plan 1999 Approval is not the best practice environmental management for this activity.
20. The disposal of waste by the First Defendant into Basamuk and Astrolabe Bays and consequently the Ramu Nickel Environmental Plan 1999 Approval is contrary to Goal 4 of the National Goals and Directive Principles of the Constitution, in that it does not promote sustainable development of the environment and the economic, social and physical well-being of people by safeguarding the life-supporting capacity of air, water, soil and eco-systems for present and future generations, and does not avoid or mitigate any adverse effects of the activity on the environment.
21. Whilst the Ramu Nickel Environmental Plan 1999 Approval was initially saved by the transitional provisions of section 136 of the Environment Act 2000, the environmental harm caused by the activity being the disposal of waste into Basamuk and Astrolabe Bays is not saved, lawful and allowed as immediately before the coming into the operation of the Environment Act 2000 the First defendant was not lawfully carrying on the activity pursuant to an approval under the repealed Acts.
22. As the activity was not being carried on by the First Defendant or anyone else under Ramu Nickel Environmental Plan 1999 Approval at the commencement of the Environment Act 2000, the activity must be subject to the Environment Act 2000, and would not be lawful under that Act, for the reasons set out in paragraphs 16, 17, 18, 19 and 20 of the Statement of Claim and ought to be restrained.
23. Further and/or in the alternative, the activity of dumping waste into the Basamuk and Astrolabe Bays by the First Defendant in reliance on the Ramu Nickel Environment Plan 1999 Approval or anything else, which in addition to the harms as set out in paragraphs 16 to 20 inclusive of this Statement of Claim will and/or will potentially cause:-
24. The First Defendant intends, unless restrained by this Court, to commit the said public nuisance and/or private nuisance and injure the Plaintiffs in their use and enjoyment of their customary land and water rights on the Rai Coast..
AND THE PLAINTIFFS CLAIM
(a) A permanent quia temet injunction to restrain the First Defendant by itself, its servants or agents or otherwise however, from committing the said nuisances and to injure the Plaintiffs in their use and enjoyment of their customary land and water rights.
(b) A declaration that the Plaintiffs ought to be consulted by the Defendants and informed on any matter concerning tailings waste disposal concerning the Ramu Nickel mine.
(c) A declaration that an activity that was permitted by an approval, permit or license under the repealed Acts that:
- (i) had not commenced at the time the Environment Act 2000 came into force on 1 January 2004, and
- (ii) was an activity that would constitute an offence under the Environment Act 2000.
Is not saved by the provisions of Section 136 of the Environment Act 2000.
(d) A declaration that the activity to be commenced by the First Defendant being the dumping of tailings and waste into the Astrolabe and Basamuk Bays is in breach of the Environmental Act 2000 and is unlawful.
(e) In the alternative to (a) a permanent quia temet injunction to restrain the First Defendant from dumping waste and tailings into the Astrolabe and Basamuk Bays in accordance with the Ramu Nickel Environmental Plan 1999 Approval or at all.
(f) Punitive damages against all Defendants
(g) Interest at 8% pursuant to the Judicial Proceedings (Interest on Debts & Damages) Act Chapter 52.
(h) Costs of this action."
Standing
II. Serious question to be tried
"For the Avoidance of doubt, a holder of an authorization instruction is entitled, to carry on any activity pursuant to or specified in the authorization instrument (including all necessary or inevitable act or works that relate to or are associated with the carrying on of such activity), and the carrying on of such act, works or activity does not constitute an offence and is not unlawful."
a. "...there are serious issues to be tried, particularly concerning whether the environmental approval for the deep sea tailings placement is lawful"(AB 404, (Vol. 2), first para.);
b. There was a serious issue in relation to the approval under section 136(3) of the Environment Act 2000 because para. (a) of that section did not apply, and "Therefore the operation of the tailings displacement was not 'saved'. (AB 404, Vol. 2, second para.). On the same page His Honour described this as raising 'important questions of interpretation' and an 'arguable case'."
"I am satisfied that important questions of interpretation of the Environment Act 2000 are raised through the Statement of Claim. The prospects of the plaintiffs succeeding cannot be dismissed at this stage as bleak. An arguable case exists. "(Appeal Book pg.404, Vol. 2).
"The defendants argue that the plaintiffs' interpretation of Section 136(3) is skewed and erroneous. Section 136(3), they argue, is irrelevant to this case as MCC's proposed deep sea tailings placement system has been authorized by the repealed Environmental Planning Act and saved under Section 136(1) of the Environment Act 2000, and therefore the carrying on of that activity cannot constitute an offence under the Environment Act.
Mr Molloy, for MCC, raised a number of significant legal arguments concerning Section 136 that seem to cast doubt on the sustainability of this aspect of the plaintiffs'case. Ms Aikung, for the Mineral Resources Authority, added weight to the argument by referring to the Environment (Permits Regulation 2002, particularly Section 28 (transitional arrangements). However, I am not dissuaded from the view I expressed when ruling on the motion for an interim injunction that important questions of interpretation of the Environment Act 2000 are raised through the statement of claim and that the prospects of the plaintiffs succeeding cannot be dismissed as bleak and that an arguable case exists.
Previously undisclosed material facts
The court now has before it a lot of affidavit material deposing to the statutory approval relied on by MCC to authorize the operation of its deep sea tailings placement system. Mr Molloy emphasized that MCC was not just relying on the statutory approvals given under the repealed Environmental Planning Act. There has been a series of approvals and amendments of approvals and a consistent course of interaction and consultation between MCC and the Director of Environment and the Department of Environment and Conservation. The defendants point in particular to a permit issued by the Director of Environment in November 2007 which specifically authorizes the construction of a deep sea tailings placement system. The consultation has continued to as recently as 10 March 2007 with a letter from the Department to MCC's project director, Dr James Wang. The defendants therefore argue that there is no case for saying that MCC's conduct could be regarded as unlawful. There can be no private nuisance or public nuisance established (they being the principal causes of action relied on by the plaintiffs) as MCC is acting under statutory authority.
Mrs Nonggorr, for the plaintiffs, counters those arguments by submitting that, though the plaintiffs still wish to argue that MCC does not have statutory approval under the Environment Act, if the court finds against them on that issue, they will argue that the existence of statutory approval does not necessarily provide a complete defence to a claim of private nuisance or public nuisance. They want to rely on the common law of nuisance – which they say has been adopted as part of the underlying law of Papua New Guinea – and the principle that statutory approval of a nuisance-generating activity is only a defence to a nuisance claim when it is an 'inevitable consequence' of the activity that has been authorized by statute.
I consider that this is an arguable issue, especially as there appears to be no provision in the Environment Act that says that the granting of an environment permit or other statutory approval indemnifies or protects the person undertaking that activity against all common law-based claims for damages arising from it. It is certainly not something that has been decided previously by the National Court or the Supreme Court. In fact there are very few reported PNG cases on the law of nuisance, just as there are very few cases in which the courts have been required to interpret and apply the provisions of the environmental laws." (Appeal bk.Vol. 12 pg. 3324, 3325).
III. Delay
Other matters raised in grounds of appeal
"Approvals, permits, licences, etc., to continue in force.
(1) Subject to this section –
- (a) an approval granted under the Environmental Planning Act (repealed); and
- (b) a permit and licence granted under the Environmental Contaminants Act (repealed); and
- (c) a permit (including a water investigation permit) issued under the Water Resources Act (repealed).
Valid and in force immediately before the coming into operation of this Act, shall –
(d) continue, on that coming into operation, to have full force and effect for the term for which they were granted or until they sooner expire or are revoked according to law as if the Act under which they were granted had not been repealed; and
(e) be deemed to be corresponding permits for the purposes of this Act and may be dealt with in accordance with the provisions of this Act as if they had been issued under this Act.
(2) Where, prior to the expiry of a permit, licence or approval referred to in Subsection (1), the holder has applied for a permit under this Act, the permit, licence or approval granted under the repealed Act shall continue to have full force and effect until the application for a permit has been determined in accordance with Sections 60 to 69 inclusive.
(3) Where, immediately before the coming into operation of this Act –
(a) a person was lawfully carrying on an activity pursuant to a permit, licence or approval under the repealed Acts which is deemed to be a permit by virtue of Subsection (1); and
(b(13)) the activity would constitute an offence under this Act, the person is entitled, subject to this section and to the permit, to carry on the activity and the carrying on of the activity does not constitute an offence.
II Does the balance of convenience favour the refusal of an interlocutory injunction more particularly the respondents alleged delay?
Conclusion
"This being an appeal against the exercise of discretion, it must I think, be shown to this Court that the Judge in Chambers exercised his discretion upon a wrong principle, has allowed extraneous or irrelevant matters to guide or affect him, mistaken the facts, or not taken into account some matter for consideration. Then and only then (Lovell v. Lovell (1950) 8 C.L.R 192 at p. 199), the lower court having been shown to be clearly wrong in its decision (Australian Coal and Shale Employees' Federation v. The Commonwealth and Others [1953] HCA 25; (1953) 94 C.L.R. 621), or it appearing that otherwise injustice will be done (Evans v. Bartlam [1937] A.C. 473 at p.480), the appellate court may exercise its own discretion in substitution for that of the lower court, if it has the material for doing so."
"there is a material difference between an exercise of discretion on a point of practice or procedure and an exercise of discretion which determines substantive rights. In the former class of case, if a tight rein were not kept upon interference with the orders of Judges at first instance, the result would be disastrous to the proper administration of justice. The disposal of cases could be delayed interminably, and costs heaped up indefinitely, if a litigant with a long purse or a litigious disposition could, at will, in effect transfer all exercise of discretion in interlocutory applications from a judge in chambers to a court of Appeal".
"only in exceptional circumstances should there be a need for intervention before it (a lower court) makes a final determination'
(my emphasis)
"that as a general rule the Supreme Court should not interfere with a National Court hearing until it had reached a conclusion....finality should normally be obtained in the National Court before appeal were sought there from".
Review of exercise of discretion by primary judge
"The appellant Court will not interfere with a discretionary judgment on a procedural matter within its jurisdiction, except where the exercise of that discretion is clearly wrong. A discretionary judgment may be set aside if an identifiable error occurred in the exercise of discretion. Alternatively, it may be set aside where there is no identifiable error, but the resulting judgment or order is "unreasonable or plainly unjust" and such that an error can be inferred. These principles are well established. We adopt a passage from Kitto J in the Australian High Court case of Australia Coal and Shale Employees' Union v The Commonwealth [1953] HCA 25; (1956) 94 C.L.R. 621 at p.627, which was adopted by Clarkson J. in Breckwoldt & Co. (N.G.) Pty Ltd v. Gnoyke [1974] PNGLR 106 at p.112 – 113:
"The decision by the primary judge to stay the action was made in exercise of a judicial discretion and I accept that in those circumstances the principles on which this Court should act are as described by Kitto J. in Australian Coal and Shale Employees' Union v The Commonwealth ... the true principle limiting the manner in which appellate jurisdiction is exercised in respect of decisions involving discretionary judgements is that there is a strong presumption in favour of the correctness of the decisions appealed from, and that that decision should therefore be affirmed unless the court of appeal is satisfied that it is clearly wrong. A degree of satisfaction to overcome the strength of the presumption may exist where there has been an error which consists in acting upon a wrong principle, or giving weight to extraneous or irrelevant matters, or failing to give weight or sufficient weight to relevant considerations, or making a mistake as to the facts. Again, the nature of the error may not be discoverable, but even so it is sufficient that the result is so unreasonable or plainly unjust that the appellate court may infer that there has been a failure properly to exercise the discretion which the law reposes in the court of first instance..."
The decisions appealed
substantially the same, the Appellants argued the appeal from each decision together.
Law on injunctions
Serious questions to be tried
"What the Plaintiff must prove is that he has a serious, not a speculative case which has a real possibility of ultimate success..."
".... a strong case which, on the evidence presented would support a permanent injunction".
Section 136 Environment Act 2000
a) the Department of Environment and Conservation approved the Ramu Nickel Environment Plan 1999 under the now repealed Environmental Planning Act. This is acknowledged by the Respondents. The Approval terms and conditions include the construction and operation of a deep sea tailings placement system,
b) there was evidence that the Approval was granted under the now repealed Environmental Planning Act,
c) before the Approval was granted the Environmental plan was independently reviewed by experts. In particular, the evidence before the primary judge disclosed the following studies:
(i) Dames Moores Report to the Department of Environment and Conservation states:
"(4) REVIEW OF DSTP DESIGN
We concur with the main features of the DSTP system as proposed, specifically the proposals for de-aeration and the outfall dept of 150m. Our own experience would lead us to some differences in design. However, we should emphasize that we do not see any "fatal flaws" in the design proposed.
(6) REVIEW OF PREDICTED IMPACTS
We agree with NSR that only impacts to the shallow environment will be localised direct disturbance and short term turbidity during installation of the scabbed pipelines. Recovery should be rapid and total.
(9) SUMMARY AND CONCLUSION
Overall, we consider that the proposed tailings system is appropriate to the situation and, in all possibility, represents the option with lowest environmental impact and lowest risk to life and property. There is potential, in our view for further optimisation of the DSTP system during detailed design."
(ii) During 2000 and 2001, the CSIRO of Australia conducted a 12 month Oceanographic Study at Basamuk which concludes that:
"The southward flow does not necessarily imply upwelling at those times because the flow could have deviated east or west near the coast.
(iii) Coffey Natural Systems Pty Ltd of Australia submitted a comprehensive review assessment which concludes that no adverse effect will result from DSTP.
(iv) HAYCO in the Report titled Ramu Nickel Deep Sea Tailings Placement System Basic Design stated at clause 3.12 that:
"The goal of deep sea tailings disposal systems is to move the tailings from the end of the outfall pipe to the deep sea ocean basins, with minimal deposition in the shallow water near the outfall. It has been observed at various outfall sites that tailings which are sufficiently fine form a density current which flows along the seabed."
(v) the report prepared by Cardino Acil who were engaged by the Department of Environment and Conservation to "....advise the Director of Environment (PNG) on the integrity of the DSTP design and the related risks with the relevant management options identified" said that "There are no matters identified in the documents provided which appear to be of sufficiently serious nature as to prevent the project proceeding."
d) the thrust of the Respondents claim is that the First Appellant, Ramu Nico Management (MCC) Ltd (MCC)'s proposed activity, being the construction and operation of deep sea tailings, is not authorised by law as it would cause environmental harm. The Respondents claim that under the Environment Act 2000, 'If there is anything going on that would be considered unlawful under the current Act, it is only saved if the Activity was actually being conducted at the time of coming into operation of the Act and that was 1 January 2004 and nothing was going on then...'
e) MCC submitted in the National Court and submitted to this Court that the Approval of the Environmental Plan 1999 is saved under section 136(1) of the Environment Act 2000 and section 28 of the Environment (Permits and Transitional) Regulation. According to those provisions, the Approval granted under the repealed Act in force immediately before the coming into operation of the new Act continued to have full force and effect and were "deemed to be corresponding permits for the purposes of the Environment Act 2000 and could be dealt with in accordance with the provisions of this Act as if they had been issued under this Act."
f) s. 136 (3) Environment Act 2000 provides that:
"136 Approvals, permits, licenses, etc., to continue in force
(3) Where, immediately before the coming into operation of this Act-
(a) a person was lawfully carrying on an activity pursuant to a permit, license or approval under the repealed Acts which is deemed to be a permit by virtue of Subsection (1); and
(b) the activity would constitute an offence under this Act,
the person is entitled, subject to this section and to the permit, to carry on the activity and the carrying on of the activity does not constitute an offence."(underlining added)
g) s.136(1) is the principal saving provision whereby Approvals granted under the repealed Acts are continued and are deemed to be corresponding Permits under the new Act. Section 136(3) deals with the situation where a permit granted under the repealed legislation authorises a certain activity but under the new Act that same activity is an offence.
h) MCC submits that section 136(3) is intended to deal with the situation where a person, at the time the Environment Act 2000 came into force, was conducting an activity under an Approval granted under the repealed Acts and that activity would constitute an offence under the new Act, that person can continue to carry out that activity. However section 136(3) has no application here as the proposed activity, being a deep sea tailing placement system approved under the repealed legislation, is not an offence under the Environment Act 2000.
i) MCC submits that section 136(3) has no application as none of the activities including the deep sea tailings disposal placement system approved under the Environmental Plan 1999 is an offence.
j) pursuant to Section 65(1) of the Environment Act 2000, the Director may grant a Permit if he is satisfied of the matters stated for the application. Upon the issue of the Permit, the Director shall specify the conditions for which the permit is granted having regard to such matters as the objects of the Act, matters of National importance, general environmental duty, relevant environmental policy; etc. Section 71 of the Environment Act 2000 empowers the Director to amend a Permit where he is satisfied of the matters set out in s. 65(1). A Permit includes an Approval granted under the repealed Act.
k) even if the Approval granted under the repealed legislation was not saved as submitted by the Respondents, there was evidence before the primary judge that MCC has other authorisation under the Environment Act 2000 and has been granted a number of permits and amendments to the existing permit as the project has progressed. Specifically, a permit was issued to MCC in November 2007 which authorises the construction of a deep sea tailings system. There was further evidence that MCC was working in close consultation with the Department of Environment and Conservation.
Public and private nuisance
"Public bodies and officials may only do acts which would be unlawful in others if they are authorised to do them by statute. Of course, as government has become increasingly regulatory and far – reaching in its effects, more and more such powers have been given. The question before the courts in tort cases of this type is whether the act in question authorised the official to commit the tort complained of.
Certain guiding principles have been worked out by the courts in order to answer this question. Either duty or a power to do the act will afford a defence. The defendant must prove that the tort would be an inevitable result of performing the act authorised: if, for instance, a local authority built an efficient electricity generating station, the fumes from which damaged crops of the plaintiff, they would only have a defence if they proved not merely that an efficient station had been built, but also that they had used all reasonable care in the light of current technical and scientific skills to prevent the commission of a tort; however, they have an absolute defence, regardless of proving these precautions, if they can discharge the very heavy burden of proving that the Act authorised them to disregard these matters."
7. General environment duty
(1) A person shall not carry out an activity that causes or is likely to cause an environmental harm unless the person takes all reasonable and practicable measures to prevent or minimise the environmental harm.
(2) .............;
(3) Failure to comply with the general environmental duty does not constitute an offence or give raise of itself to a right to civil remedy, but compliance with the duty may be enforced by –
(a) an Environment Protection Order; or
(b) a Clean –up Order; or
(c) an Emergency Direction.
(4) Where in a proceeding it is alleged that a person failed to comply with the general environmental duty by causing environmental harm, it will be a defence if the harm is caused in the course of complying with an Environmental Code of Practice or authorized to be caused under –
(a) an Environment Policy; or
(b) a condition of an environment permit; or
(c) an approved environmental improvement plan; or
(d) an Environment Protection Order; or
(e) an Emergency Authorisation.
"where a statute empowering the execution of a variety of works gave to the statutory authority wide powers, which necessarily involved the possibility of interference with the rights of others, and expressly provided a remedy by way of compensation, a person who sustained injury through the carrying out of operations authorised by the statute had no right of action for nuisance; and therefore, as the injury sustained by the plaintiff was occasioned by a normal drainage operation, carried out in the usual way, under the powers given to the catchments board by s. 34 (1) of the Land Drainage Act, 1930, the plaintiff's only remedy for the injury of which he complained of was to claim compensation under s. 34 (3) of the Act."
Grounds of Appeal
" 3. Grounds
His Honour erred in that he should have found that the Respondents had not established a prima facie cause of action or a seriously arguable case of either private or public nuisance actual or threatened.
His Honour erred in that he should have found that the First Appellant had an Approval under the Environmental Planning Act Ch. No. 370 which by virtue of the transitional and savings provisions was deemed a Permit under the Environment Act 2000 permitting it inter alia to construct and operate a deep sea tailings placement system as part of the Ramu Nickel Mine Project.
His Honour misconstrued section 136(3) of the Environment Act 2000 in that he should have found that that provision only applies to an activity that is an offence under the Act and nothing the First Appellant was doing or intended to do was such an offence.
His Honour erred in that he should have found that the Respondents had not established they had sufficient stand.
His Honour erred in failing to find that having regard to the stage of construction of the Ramu Nickel Mine Project, the First Appellant's plan to install the deep sea tailings placement system in march 2010, the scheduled completion of the project in 2010 after years of construction, the timing of the Respondents' application, the fact that some of the affidavits relied on by the Respondents had been sworn in 2009 and only filed and served in March 2010, that the balance of convenience favoured refusing an interlocutory injunction.
His Honour erred in that he should have refused the interlocutory injunction on the grounds of the Respondents' delay.
His Honour erred in that he should have refused the interlocutory injunction on the grounds that not all Respondents had provided undertakings as to damages; the undertakings which were provided could not possibly compensate the First Appellant and the Fifth Appellant for the enormous loss they would suffer in consequence of the granting of the injunction, and that accordingly it was unjust to grant the injunction.
and as to the judgment of 14 April 2010. His Honour failed in law and in fact to exercise his discretion judiciously in that –
His Honour should have found that the interlocutory injunction granted on 19 March 2010 had been granted on an erroneous legal basis including a misinterpretation of the meaning and application of section 136(3) of the Environment Act 2000.
His Honour should have found that the interlocutory injunction had been granted on an erroneous factual basis in that the First Appellant had a Permit or Permits under the Environment Act 2000 allowing the activities it was carrying out or intending to carry out in respect of the construction and operation of a deep sea tailing placement system.
The Appellants repeat each of the above grounds relied on in support of the appeal against the granting of the interlocutory injunction on 19 March 2010."
Law
"This being an appeal against the exercise of discretion, it must I think, be shown to this Court that the Judge in Chamber exercised his discretion upon a wrong principle, has allowed extraneous or irrelevant matters to guide or affect him, mistaken the facts or not taken into account some matters for consideration. Then and only then (Lowell v Lowell (150) 81 C.LR.513, at p.518. House v The King (1936) 56 C.L.R 499 at p.504, the Lower Court having been shown to be clearly wrong in its decision (Australian Coal and State Employee's Federation v The Commonwealth and Others [1953] HCA 25; (1953) 94 C.L.R. 621, or it appearing that otherwise injustice will be done (Evans v Bartlam [1937] A.C. 473 at p.480, the appellate Court may exercise its own discretion in substitution for that of the lower court, if it has the material to do so".
"The appeal... is an appeal against the exercise of discretion and for the Appellate Court to substitute its discretion for that of the Judge appealed from, it must be shown that the Judge appealed from exercised his discretion upon a wrong principle, allowed him, mistook the facts or did not take into account some matters for consideration"...
"Australian decisions show that an appellate court will exercise particular caution in reviewing interlocutory decisions of lower courts particularly those involving exercise of discretion in matters of practice and procedure. A statement often cited is that of Jordan J. In Re the Will of Gilbert (1946)...(NSW) LR 318:
"I am of the opinion that... there is material difference between an exercise of discretion on a point of practice or procedure and or exercise of discretion which determines substantive rights. In the former class of case, if a tight rein were not kept upon interference of the orders of Judges of the first instance, the result would be disastrous to the proper administration of justice. The disposal of cases could be delayed interminably, and costs heaped up indefinitely, if a litigant with a long purse or litigious disposition could, at will, in effect transfer all exercise of discretion in interlocutory applications from a Judge in Chambers to a Court of Appeal."
In Gerard v Email [1993] 32 NSWLR 662 at p.668, Kirby ACJ notes that appellant Courts must pause long and hard before disturbing interlocutory orders and especially in matters relating to practice and procedure and costs."
Interlocutory Injunctions
Serious question to be tried
Section 136 Environment Act 2000
"The Department of Environment and Conservation approved the Ramu Nickel Environment Plan 1999 now repealed Environment Planning Act. This is conceded by the Respondents. The approved terms and conditions included permission for the construction and operation of a deep sea tailings placement system (DSTP).
There was evidence that the Environmental Plan Approval was granted under the repealed Environmental Planning Act. Before that approval was granted the Environmental plan was independently reviewed by Dames and Moore.
Subsequently, many aspects of the Environmental plan have been independently reviewed by the following experts:
Dames and Moor Report to DEC states:
"(4) REVIEW OF DSTP DESIGN
We concur in the main features of the DSTP system as proposed, specifically the proposal for de-accretion and the outfall depth. of 150 m. Our own experience would lead us to some differences in design. However, we should emphasize that we do not see any "fatal flaws" in the design proposed.
(6) REVIEW OF PREDICTED IMPACTS
We agree with NSR that only impacts to the shallow environment will be localized direct disturbance and short term during installation of the pipelines. Recovery should be repel and total.
(9) SUMMARY AND CONCLUSION
Overall, we consider that the proposed tailings system is appropriate to the situation and, in all possibility, represents the lowest environmental impact and lowest risk to life and property. There is potential, in my view for further optimization of the DSTP system during detailed design."
During 2000 and 2001, CSIRO of Australia conducted a 12 month Oceanographic study at Basamuk which concluded that:
"The southward flow does not necessarily imply upwelling at that time because the flow could have deviated east or west near the coast."
In the HAYCO Report titled Ramu Nickel Deep Sea Tailings Placement System Basic Design stated at clause 3.12 that:
"The goal of deep sea tailings systems is to move the tailings from the end of the outfall to the deep sea oceans basins with minimal deposition in shallow water near the out fall. It has been observed at various out fall sites those tailings which are sufficiently fine form a density current which flows along the seabed."
"There are no matters identified in the documents provided which appear to be of sufficiently serious nature as to prevent the project proceeding."
that under the Environment Act 2000, "If there is anything going on that would be considered unlawful under the current Act, it is only saved if the activity was actually being conducted at the time of coming into operation of the Act and that was 1 January 2004 and nothing was going on then..."
Permit under the Environment Act 2000
Environment Act 2000, and the Director has granted a number of permits and amendments to the existing permit as the project progressed. Those permits and amendments are as follows:-
23 October 2006,
7 November 2007, and
10 August 2009,
Common law torts of public and private nuisance
"Public bodies and officials may only do acts which would be lawful in others if they are authorized to do them by statute. Of course, as government has become increasingly regulatory and far – reaching in its effects, more and more such powers have been given. The question before the courts in tort cases of this type is whether the Act in question authorized the official to commit the tort complained of.
Certain guiding principles have been worked out by the courts in order to answer this question. Either duty or a power to do the act will afford a defence. The defendant must prove that the tort would be an inevitable result of performing the act authorized: if, for instance, a local authority built an efficient electricity generating station, the fumes from the damaged crops of the plaintiff, they would only have a defence if they proved not merely that an efficient station had been built, but also that they had used all reasonable care in the light of current technical and scientific skills to prevent the commission of a tort; however, they have an absolute defence, regardless of proving these precautions, if they can discharge the very heavy burden of proving that the Act authorized them to disregard these matters."
Section 7 of the Environment Act 2000
"7. General environment duty
A person shall not carry out an activity that causes or is likely to cause an environmental harm unless the person takes all reasonable and practicable measures to prevent or minimize the environmental harm.
...................;
Failure to comply with the general environmental duty does not constitute an offence or given raise of itself to a right to civil remedy, but compliance with the duty may be enforced by –
an Environment Protection Order; or
a Clean-up Order; or
an Emergency Direction.
Where in a proceeding it is alleged that a person failed to comply with the general environmental duty by causing environmental harm, it will be a defence if the harm is caused in the course of comply with an Environmental Code of Practice or authorized to be caused under –
an Environment Policy; or
a condition of an environment permit; or
an approved environmental plan; or
an Environment Protection Order; or
an Emergency Authorization."
"(1) where a statue empowering the execution of a variety of works gave to the statutory authority wide powers, which necessarily involved the possibility of interference with the rights of others, and expressly provided a remedy by way of compensation, a person who sustained injury through the carry out of operations authorized by the statute had no right of action for nuisance; and therefore, as the injury sustained by the plaintiff was occasioned by a normal drainage operation, carried out in the usual way, under the powers given to the catchments board by s.34 (1) of the Land Drainage Act, 1930, the plaintiff's only remedy for the injury of which he complained of was to claim compensation under s.34 (3) of the Act."
"a) The Respondents allege the first Appellant is about to commit gross private and Public nuisances in the Basamuk and Astrolabe Bays and such activity are unlawful.
(b) The Respondents allege based on scientific evidence contained in the affidavits that the activity of dumping waste into the Basamuk and Astrolabe Bays by the First Appellant in reliance on the Ramu Nickel Environmental Plan 1999 Approval or anything else, will and/or will potentially cause (relying on the Lutheran report/Affidavit of Dr Amanda Reinhelt-Brushett/Affidavit of Dr Greg Brunskill):-
Ore slurry deposits and turbidity in shallow habitats
Condition suitable to Tsunamis
Biological and spatial interference on shallow water and deep water fishes and fauna
Shallow water habitat change and burial of fauna
Toxic effects from tailings
Tailings brought onshore from upwelling and currents
Turbidity Plumes of sediment, both toxic and otherwise, spreading out horizontally over hundreds of kilometers.
Adverse biological impacts on the Goldband Snapper and the Ruby Snapper.
Morality of Benthic Fauna over a large area.
Increased bioconcentration of trace metals and eco-toxicological risks to the food web.
Destruction to essential services being the new Telikom cables.
Irreversible damage to Corals, including but not limited to their breeding cycles.
Elevated levels of chromium, iron, manganese, nickel and mercury in the marine environment as well as extreme high levels of ammonia which; will be ingested by benthic fauna (bottom of the food chain),may/will be acutely and chronically toxic to fish, crustaceans and cephalopods,will create sub-lethal affects as well, including reduced growth and gill damage.
(c) The Respondents seek as a result of this nuisance a permanent anticipatory injunction, and the respondents say that the First Appellant cannot rely upon the defence of statutory authority as although the First Appellant has an Environmental permit, such permit does not authorize the nuisance, as the permit was granted on the basis of the miner's assertion that there would be no environmental harm.
73. The Respondents submit that:-
The disposal of waste by the First Appellant into Basamuk and Astrolabe Bays and consequently the Ramu Nickel Environmental Plan 1999 Approval is contrary to Goal 4 of the National Goals and Directive principles of the Constitution and the scheme and spirit of the Environmental Act 2000 which is an act to give effect to the Fourth National Goal and Directive Principle of the Constitution, in that it does not promote sustainable development of the environment and the economic, social and physical well-being of people by safeguarding the life-supporting capacity of air, water, soil and eco-systems for present and future generations, and does not avoid or mitigate any adverse effects of the activity on the environment.
This activity of disposing tailings and waster into Basamuk and Astrolabe Bays by the First Appellant and will adversely affect matters of national importance within the meaning of Section 5 of the Environmental Act 2000, being that these activities will adversely effect:-
The preservation of Papua New uinea traditional social structures; and
The maintenance of sources of clean water and subsistence food sources to enable those Papua New Guineans who depend upon them to maintain their traditional lifestyles; and
The protection of areas of significant biological diversity and the habitats of rare, unique or endangered species; and
The recognition of the role of land-owners in decision-making about the development of the resources on their land; and Responsible and sustainable economic development.
The uncontested Lutheran Church commissioned independent report predicts that this disposal of waste by the First Appellant into Basamuk and Astrolabe Bays and consequently the Ramu Nickel Environmental Plan 1999 approval does not protect the environment from harm and is likely to cause Environmental and or serious environmental harm, and consequently this disposal is unlawful and contrary to ss7, 10 and 11 of the Environment Act 2000.
This disposal of waste by the First Appellant into Basamuk and Astrolabe Bays and consequently the Ramu Nickel Environmental Plan 1999 Approval will adversely affect the beneficial value of the environment within the meaning of the Environment Act 2000 and will be detrimental to ecological health, public benefit, welfare, safety, health and aesthetic enjoyment and which requires protection from environmental harm.
This disposal of waste by the First Appellant into Basamuk and Astrolabe Bays and consequently the Ramu Nickel Environmental Plan 1999 Approval is not the best practice environmental management for this activity.
Further, and/or in the alternative, whilst the Ramu Nickel Environmental Plan 1999 Approval was initially saved by the transitional provisions of section 136 of the Environmental Act 2000, it is the Respondents' submission that the First appellant's proposed dumping and the consequential the environmental harm caused by the activity being the disposal of waster into Basamuk and Astrolabe Bays is unlawful and not saved and allowed as immediately before the coming into the operation of the environmental act 2000, the first Appellant was not lawfully carrying on the activity pursuant to an approval under the repealed Acts.
As the activity was not being carried on by the First Appellant or anyone else under Ramu Nickel Environmental Plan 1999 Approval at the commencement of the Environmental Act 2000, the Activity must be subject to the Environmental Act 2000, and would not be lawful under that Act and out to be restrained.
His Honour considered in his decision on 19 March 1020 over 2 pages that the Respondents had arguable case. His Honour considered in his decision on 14 April 2010 over three pages of judgment the submissions by all parties and then found arguable case. There is an abundance of evidence that environmental damage/nuisance will be caused – so the trial judge found arguable case as whilst there may be a permit the question is whether the nuisance caused is the "inevitable consequence of the activity".
The appellants have NOT even appealed this basis for arguable case. All they have said that the trial judge failed to find that their permit authorized them to construct the system. This is not true – the judge recognized that they have an approval but the question for the action is whether the harm is authorized.
There is nothing in the Appellants arguments that disturb that view.
The Respondents have an arguable case for nuisance and for declaratory orders involving the construction of instruments made under the Environment Act 2000 and for breaches of that Act. There are no merits in these grounds and they ought to be dismissed.
The Respondents submit the Court should refer to 2 separate but important pieces of Legislation in consideration whether there are serious issues to be tried.
Environmental Act 2000
The Environmental Act 2000 is the Act which gives effect to NGDP 4 of the Constitution and also the Act which is to protect the environment from harm. We draw your attention to section 4 of the Act which sets out its objects.
Justice will be done if a decision is made by this Court that reflects the objects of this Act and not the objective of development at whatever cost.
Section 25 of the Constitution places an obligation on all governmental bodies, including the court, to give effect to the National Goals and Directive Principles, and the relevant NGDP here is Goal 4.
"Natural resources and environment.
We declare our fourth goal to be for Papua New Guinea's natural resources and environment to be conserved and used for the collective benefit of us all, and be replenished for the benefit of future generations.
WE ACCORDINGLY CALL FOR –
wise use to be made of our natural resources and the environment in and on the land or seabed, in the sea, under the land, and in the air, in the interests of our development and in trust for future generations; and the conservation and the replenishment, for the benefit of ourselves and posterity, of the environment and its sacred, scenic, and historical qualities; and all necessary steps to be taken to give adequate protection to our valued birds, animals, fish, insects, plants and trees."
Section 25(3) obliges a decision maker, whatever the source of his power to give effect to the NGDP, so long as that is what parliament intended.
Parliament clearly intended for the environment to be protected from harm and for those decision makers to take a pre-cautionary approach. We refer you to a passage taken from the Constitutional Planning Committee's report in 1975, that was also referred to His Honour.
It is in the interests of justice to leave the injunction in place until the substantive hearing to give effect to NGDP4."
"Sch.2.2.2 – Adoption of a common law
preservation of status quo,
prejudice,
delay,
the interest of the respondents (standing),
conduct of the parties; and
whether damages would be an adequate remedy and whether an undertaking as to damages was given.
Formal Orders
____________________________________
Posman Kua Aisi Lawyers: Lawyers for the First Appellant
Allens Arthur Robinson: Lawyers for the Second Appellant
Solicitor-General: Lawyer for the Third, Fourth and Fifth Respondents
Nonggorr William Lawyers: Lawyers for the Respondents
PacLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.paclii.org/pg/cases/PGSC/2010/22.html