You are here:
PacLII >>
Databases >>
High Court of Solomon Islands >>
2021 >>
[2021] SBHC 107
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Help
LB Construction and Joinery v Attorney General [2021] SBHC 107; HCSI-CC 208 of 2019 (6 August 2021)
HIGH COURT OF SOLOMON ISLANDS
Case name: | LB Construction and Joinery v Attorney General |
|
|
Citation: |
|
|
|
Date of decision: | 6 August 2021 |
|
|
Parties: | LB Construction and Joinery v Attorney General |
|
|
Date of hearing: | 2 July 2021 (closing Submissions) |
|
|
Court file number(s): | 208 of 2019 |
|
|
Jurisdiction: | Civil |
|
|
Place of delivery: |
|
|
|
Judge(s): | Keniapisia; PJ |
|
|
On appeal from: |
|
|
|
Order: | The claim is therefore dismissed in its entirety with cost. |
|
|
Representation: | Mr. N. Laurere for Claimant Mr. S Banuve, Solicitor General for the Defendant |
|
|
Catchwords: |
|
|
|
Words and phrases: |
|
|
|
Legislation cited: |
|
|
|
Cases cited: | |
IN THE HIGH COURT OF SOLOMON ISLANDS
CIVIL JURISDICTION
Civil Case No. 208 of 2019
BETWEEN
LB CONSTRUCTION AND JOINERY
Claimant
AND:
ATTORNEY GENERAL
(Representing Ministry of Communication and Aviation)
Date of Hearing: 2 July 2021(Closing Submissions)
Date of Judgment: 6 August 2021
Mr. N. Laurere for Claimant
Mr. S Banuve, Solicitor General, for Defendant
JUDGMENT ON BREACH OF CONTRACT CLAIM
- LB Construction and Joinery, alleged it completed a road upgrade work for the government. But the government is refusing to pay for
the work it did. LB Construction and Joinery (“the company”) put the contract payment dues (arrears) for the work it
did at $3,023,200.00. The company commenced the job on or around 15th March 2013. And completed the job 3 months later around June 2013. Ever since, the company’s efforts to get its contract payment arrears of $3,023,200.00 were futile. The prime relief sought in the claim is to recover the said amount in damages for breach of contract.
- The company came to Court seeking to recover the $3,023,200.00, based on what it alleged was a verbal agreement. The verbal agreement all begun on or around 15/03/2013. On that day, the then Minister of Aviation, Mr Walter Folotalu made a patrol around the outer perimeter fence of Henderson International
Airport. As a former aviation officer himself, Minister Folotalu was taking a keen interest on the Ministry’s responsibilities.
- Minister Folotalu noted the deteriorating state of the road conditions around the airport perimeter fence. The Minister had serious
concerns about the safety and security of the airport perimeter fence road. The safety and security concerns for the road demands
that there was urgency to engage a contractor to start the job quickly. The road and the drainage must be repaired to control debris
during wet season. And to allow direct access to the nearby Henderson police post. Also to allow public access to the airport so
as to prevent burglars into the airport facilities. Furthermore, repairing the road will also help to avoid the urgent threat from
World War 2 unexploded bombs.
- Noting these serious concerns from his patrol, the Minister met up with an officer from the company. The company official was doing
some work on earth moving and excavation around the airport vicinity. So the Minister made a decision there and then to engage the
company for the job. And asked the company to start the job straight away.
- The Minister returned to the office. And wrote straight to his Permanent Secretary (“PS”), Mr Lomu the same day of 15/03/2013. The Minister instructed PS Lomu in the letter, that he had verbally engaged the company to do the road repair. The Minister was
fully cognisance of the tendering and financial instruction requirements for the award of public contracts. So the Minister in the same letter urged his PS, Mr. Lomu, to immediately pursue
tendering and financial instruction requirements to seal the engagement he made with the company for the job. The relevant paragraph of the Minister’s letter[1] is: -
- “This note therefore carries my instructions that, you are to immediately pursue formalities with the appropriate tender board
to offer the award to LB construction who is currently undertaking re-construction of the said road. I would appreciate the financial
controller to this process to ensure the financial instructions are comfortably met.” (Underlined my own emphasis).
- Whilst the tendering and financial instruction requirements are yet to be settled, the company had already commenced work, in reliance on the verbal arrangements settled with the
Minister during the Minister’s patrol discussions. As it turned out, the tendering and financial instruction requirements of the government were never activated. But the company alleged it went ahead and completed the job. The company alleged
it completed the job around June 2013. But never got paid for the job. All attempts to get payment hit deaf ears, the company says.
Issues
- The issues were agreed and are re-stated as follows:-
- (i) Whether the contract amount (consideration) was SBD $3,023, 200.00?
- (ii) Whether the Ministry of Infrastructure Development (“MID”) assessed the contract amount in the sum of SBD $3,023,200.00?
- (iii) Whether the contract amount ($3,023,200.00) claimed by the claimant may be construed as a guide or a ceiling only?
- (iv) Whether the contract could be avoided by both the Ministry of Aviation (“MA”) and MID having assessed the contract
amount, but failing to obtain the endorsement of the Minister of MID, a requirement not ordinarily known to the claimant, but known
so well by the defendant, including the responsible officers of the MID, at the material time of contract and assessment of the contract
amount?
- (v) Whether the defendant could avoid the contract by failing to comply with its own requirement, by not processing the contract
through its own contractual tender board, a requirement not ordinarily known to the claimant at the time of contract, but known so
well by the defendant, including responsible officers of the MID at the material time of contract and assessment of the contract
amount?
- (vi) Whether the principle in the ruling in Lebaro v AG [2016] SBHC 185; HCSI – CC 64 of 2016 is on point and is a classic case on the issues at hand?
With consent of Counsel, I added two more issues. First is “Whether the verbal agreement the Minister made with the company and the Minister’s letters of 15/03/2013 and 24/04/2013 will legally bind the state/defendant, notwithstanding the non-compliance to public tendering and financial instruction requirements?”
Secondly, “Whether the said verbal agreement is legally binding on the state/defendant, in view of the urgency then existing, thereby
justifying non-compliance to public tendering and financial instruction requirements (waiver)?”
Case for the Company
- The company relied on the verbal agreement Minister Folotalu made with its official on 15/03/2013. And also on the letter the Minister wrote on the same day of his patrol, as well as the letter of 24/04/2013[2]. The company owner, Mr Wanefalea, gave oral evidence that one week after 15/03/2013, the Ministry called him back to a meeting to see the Bill of Quantity (“BOQ”). Copy of the BOQ is at Pages 27 - 29 of
Trial Book (TB). From the BOQ, the company (Mr Walefalea) knew about the contract price and tasks to undertake in the road repair work. The contract price in the BOQ is set at $3,023,200.00. The length of the road in the BOQ is 3.5 Km. Mr Wanefalea said in his oral evidence that 3.5 Km was a typing error. It should be
2.5km only, because that is the actual length of the road the company completed.
- Mr Wanefalea said in his evidence in chief that, at the meeting he asked the Minister about the contract formalities, saying the
formalities were not new to him, having undertaken two previous contracts with the MA. Mr. Wanefalea however did not wait for the
formalities but took the Minister’s assurance to heart and commenced work. The Minister’s assurance was - the formality will be pursued, but the company can go ahead with the work[3]. Mr. Wanefalea had no doubt. He had no reason to question anything when the Minister was involved. He commenced work, having faith
in the Minister’s assurance. He went away, did the work, based on the Minister’s assurance and executed the activities
contained in the BOQ. And after having completed the work, his request for payment hit deaf ears.
- Mr Wanefalea continued in his evidence in chief that he went to the PS, Mr. Lomu and asked why the MA did not pay him. The PS, Mr.
Lomu told Wanefalea that: “The Ministry has no budget for the work”. Mr. Wanefalea relayed the same to the Minister.
The Minister told Mr. Wanefalea: “You tell PS Lomu to do the formalities. I will look for the money”. Mr Wanefalea knew
about the formalities and about the Central Tender Board (“CTB”), when his lawyer asked him in examination in chief:
“You know about CTB?” Mr. Wanefalea’s answer was “Yeah me save (Yes I know).” Mr. Wanefalea knew because
he had done two previous contracts for the MA. And in the two previous jobs, Mr. Wanefalea signed contracts with the CTB –
he says in his evidence in chief. And also says he knew because he used to work for Chengs, whenever Government awarded Chengs road
construction service contracts.
- Mr. Wanefalea’s lawyer continued to ask him, “So you know about any reason for not complying with the CTB?” Mr.
Wanefalea’s answer was: “I expected the CTB requirements, but they say they will do a waiver, because of the urgency
from the bomb threat, so that no intruders can come inside”. Mr. Wanefalea then said “I do not know anything about the
system”. Mr Wanefalea just believed on the waiver promise consistent with the Minister’s assurance. Mr Wanefalea could
not pin point in evidence, who promised the waiver and who gave him the BOQ document. He nevertheless had possession of the BOQ.
- Mr. Wanefalea pinned his hope on the Minister’s involvement and assurance. So he did not meet any of the procurement requirements,
inclusive of the CTB requirement. Yet went ahead in the strong belief that Minister’s assurance and the promised waiver were
more than enough. The Minister made the assurance. A Ministry official who met with Mr. Wanefalea at the meeting held one week after
15/03/2013 gave the waiver promise. Mr. Wanefalea could not recollect the identity of the officer, who made the waiver promise.
- The case for the company was simple. The Minister made a verbal agreement. The Minister gave the assurance. A Ministry official promised
a waiver of tendering requirements. And the PS, Mr. Lomu was to pursue the formalities. So the company went ahead and completed the
job. But never got paid for the job. So far as the company was concerned, the Minister’s verbal agreement followed by two letters
was the valid contract. Even if government officials in the MA and or MID have failed to activate the public procurement requirements
(tendering and financial instruction requirements), failure of the officials cannot affect a valid contract that existed between
the MA and the company, upon the Minister’s verbal agreement. The company relied on the ratio decidendi in Lebaro[4] that – “...contract law cannot be affected by the failure of government agencies to adhere to its strict controls under the financial
regulations when contracts or variations are awarded to strangers to the financial instructions, strangers who are not subject to
such instructions. The contract is unaffected by unilateral breach of the government financial instructions, if that be the case,
on the part of one contracting party here, the Ministry of Tourism. The Ministry cannot take advantage of its own failings, as it
seeks to do here. Such breach of financial instructions does not impinge on the contractual relations which I have found between
the parties”
Case for the Government/Defendant
- The MA did not initiate this particular project (job). The Ministry has no record of the job, being awarded to the company. There
was no award of the job to the company by the CTB or the Ministry’s internal tender board. The Ministry’s internal tender
board could not have possibly awarded this contract, because the contract sum exceeded $500,000.00. The tendering and financial instruction requirements were not followed in the awarding of this job. The non-compliance to the CTB tendering and financial instruction requirements
(public procurement requirements) was very clear. The company alleged it went ahead and completed the job. But the MA could not ascertain,
the completion of the job. There is no record of verification – no work completion certificate was executed. Lack of record means that the MA does not know who offered the contract to the claimant (the CTB or MA’s internal tender board).
What kind of work was offered under the contract? What was the price agreed for the work under the contract?
- The Government’s position is that there was no valid contract. The Minister’s verbal agreement and the two letters did
not constitute a valid contract. The Minister has no power to make a contract for the MA, where the work involves road, without consulting
with the Minister of MID. The Government is not liable to pay damages to the company as sought in the reliefs for compensation for
breach of contract in the sum of $3,023, 200.00. The Solicitor General submitted that the case of Lebaro could be distinguished on the contextual facts. And has no place in the contextual facts of this case, to support the company’s
case.
Courts Analysis
- Without digging further into the evidences produced by both sides the following facts can be settled on the available evidence without
much dispute: -
- (i) The Minister made a verbal agreement with the company after verbal discussions were confirmed in the Minister’s letters/memo
dated 15/03/2013 and 24/04/2013. See also Agreed Fact Number 3 at Page 10 of TB, essentially reflecting the same.
- (ii) Though the Minister gave directives for formalising his verbal agreement under tendering and financial instruction requirements,
these requirements were not complied with by PS, Mr. Lomu and his officials and or relevant officials in the MID and or MA.
- (iii) Though Mr Wanefalea knew about the CTB requirements having undertook two previous jobs, for the MA, and had worked with Chengs
formerly, he truly and verily believed the Minister’s assurance (repeat and reaffirm paragraphs 9 and 13). So went ahead and
begun work without due adherence to formalities (CTB requirements). It was his side of the bargain to do the job. And the government’s
side of the bargain (Minister’s assurances) was the obligation of the PS, Mr. Lomu and Ministerial officials.
- (iv) Mr Wanealafa maintained that his task was to do the work as verbally instructed by the Minister (followed by letters of 15/03/2013 and 24/04/2013). And the due process to be completed by PS Lomu. But that the company should not be held accountable due to neglect or omission
by the PS, Mr. Lomu and his officials to activate the CTB requirements. The company’s verbal contract with the Minister, stands
superior to the neglect and omissions on the part of PS Lomu and his officials. I can summarise Mr. Wanefalea’s attitude in
pijin. “For follom olketa requirements blo CTB or public tendering hem work blo Ministry. Mi duty blo me hem for duim work
where Minister talem mi for duim.” – “My task is to complete the road, as verbally agreed with the Minister. The
Ministry’s task is to comply with public tendering and financial instruction requirements”.
- (v) In spite of the Ministry’s non-compliance to tendering and financial instruction requirements, Mr. Wanefalea says his company has a legally binding contract based on the Minister’s verbal agreement cemented
by two subsequent letters (Foot note 1 and 2). The Minister’s verbal agreement and assurance comes first. The Government’s
tendering and financial instruction requirements for award of a public contract comes second. Officials neglect to the tendering and financial instruction requirements
should not affect a valid contract, the Minister had concluded with the company. This is the essence of the claimant’s case.
And the evidence he connects to the Minister’s verbal contract and assurances.
- (vi) The MA denies there was a valid contract and that the Minister’s purported verbal agreement cannot constitute a valid
contract. For the Ministry has no record of the awarding of this particular contract. And that the Minister has no power to make
contracts for the Ministry; except the CTB, where the contract sum exceeds $500,000.00. The Minister’s verbal agreement was made without due adherence to tendering and financial instruction requirements. The current
PS, Mr. Virivolomo gave evidence that the MA did not initiate this project. The MA has no record of this project. And the verbal
contract made without the procurement process, missed out on five important valid requirements for a public contract award by the
state. They are (i) tender dossiers or tender instructions to bidders; (ii) special conditions of contract; (iii) drawings; (iv)
specifications and (v) written agreements/contracts. Hence the verbal agreement is null and void and not legally binding on the MA.
Lebaro precedent – context - valid written contract to start with
- Claimant relied heavily on the ratio decidendi in the case of Lebaro. And submit that, the officials may have not complied with financial instructions and tendering requirements. But government cannot
rely on its officials’ failings to avoid a valid contract. This is a strong argument. So I need to look at the context, in
which, the Judge made the ratio decidendi which claimant relied on as precedent.
- In Lebaro, there was a written contract to start with. The Government entered into a written contract with Lebaro. The responsible ministry
was Ministry of Culture and Tourism. The accounting officer was the PS of that Ministry. The written contract gives certainty as
to the major terms of the contract. The major terms like scope of work to do, consideration for the work, supervision of the work
and variation of the work. The agreed price was $1,007,563.32, inclusive of the variation price. The work required was to supply materials and to do repair work on Boys Dorm Double floor and Single
floor, at Panatina Campus. The materials were supplied and work completed, as certified by the supervising architect. The completed
work includes work executed by virtue of contract variation. And payments were raised by the responsible Ministry of Tourism. Part
payments were made by the Ministry of Finance. The remaining payment was $767,155.24. The Government refused to pay the outstanding, saying the variation amount of $473,323.15 was not properly made according to financial instructions. Lebaro took court action to recover outstanding contract payments. Counsel
for the Attorney General argued that variation was not properly done, by responsible Ministry officials according to requirements
in the financial regulations. And so the variation contract sum of $473,323.15 cannot legally bind the state.
- Court found that variation was regulated under the terms of the written contract (contract). The Appendix to the contract provides
for how variation was to be done and who to do it. Court found variation followed what became a term of the written contract. The
term is that; the supervising architect may endorse variation. And if he does, that is enough because he represents the responsible
PS, as agent – has ostensible authority to vary the contract for and on behalf of the principal (Ministerial Tender Board). Everything that happened were executed
according to the terms of the written contact – materials were supplied, work was completed as verified by the supervising
architect and variation endorsed by the agent of the Ministerial Tender Board, as provided for in the variation terms in the Appendix
to the written contract. And so payment was processed by the accounting officer – the PS of the Ministry of Tourism. The Ministry
of Finance already made part payment to Lebaro. The Government refused to make the outstanding payment, saying variation of the written
contract, did not comply with financial regulation requirements. In the context discussed herein, Court says government was not allowed
to bring in arguments that financial regulation requirements were not followed by government officials. And to say that there was
no valid contract, when in fact, variation took place, according to express terms in the Appendix to the already executed valid contract.
Court relevantly said: -
- “These financial mechanisms are not the responsibility of the contracting party (with the ministry and government agencies)
to see to their application, the responsibility rests with the individuals in the department. For contract law cannot be affected
by the failure of the government agencies to adhere to its own strict controls under the financial regulations when contracts or
variations are awarded to strangers to the financial instructions, strangers not subject to such instructions.”
- The contract is unaffected by unilateral breach of the government financial instructions, if that be the case, on the part of one
contracting party here, the ministry of tourism. The ministry cannot take advantage of its own failings, as it seeks to do here.
Such breach of financial instructions does not infringe on the contractual relations which I found between the parties”
- It was clear on the facts and evidence before the Judge that Counsel for the Attorney General was putting forward an untenable case.
There was a written contract to start with. The written contract had an Appendix to it that provides for variation - variation was
a term in the contract. Variation was made consistent with the variation term of the contract. When there is a written contract,
it means the financial instructions and tendering requirements (public procurement procedures and requirements) were already adhered
to. So a binding contractual relationship existed between the parties. And that is why part payment was already processed and paid.
Counsel should not be making arguments on non-compliance to financial instruction requirements. Those requirements were already complied
with culminating in the execution of the written contract. Thereafter implementation of the contract was now governed by the terms
of the written contract. Court says it was not open for the government to interfere with a valid contract, by raising non-compliance
issues, regarding the variation that occurred. Variation was a matter for contract. The pre-requisite for the ratio decidendi in Lebaro was, there must be a written contract to start with. Once there is a written contract, it means all public contracting requirements (tendering and financial instruction requirements)
were fulfilled. And it means parties have a valid, binding and legally enforceable contractual relationship. And the contract is self-executory in terms of how to vary and who to vary. Court found that variation was properly made in line
with the variation terms of the contract. And government cannot interfere with a valid contractual relation by re-inventing the wheel
(insisting on requirements that were already adhered to prior to the contract).
Context of this case different
- The opposite is the context in the facts and evidence before me here. There was no written contract to start with. No written contract means the public procurement requirements (tendering and financial
instructions) were not complied with. And it means there is no valid, binding, and legally enforceable contractual relationship between
the MA and the company. Because of lack of written contract, there is no certainty as to the major terms of the purported verbal
agreement the Minister entered into with the company. The crucial terms like scope of work to do, price for the work to do, supervisors of the work and certification for when work was
completed. Collectively the evidence on the verbal agreement and the two letters lacked certainty as to these major terms of the
verbal contract.
- So what claimant did was to pull in a BOQ to say that the price and work to do pursuant to the Minister’s verbal engagement are contained in the BOQ. In the BOQ the road was 3.5 Km long, the tasks
were listed and the price was put at $3,023,200.00. The current PS explained that the BOQ is normally an estimate for a particular project. This accords well with the evidence of Mr.
Wanefalea, where he says the road was only 2.5 Km not 3.5 Km as it appears on the BOQ. Mr. Wanefalea says it was a typing error because
the actual length of the road he constructed was 2.5 Km not 3.5 Km. Mr. Wanefalea is not the author of the BOQ. So how could he credibly
say it was a typing error? The only logical explanation would rest with the current PS’s explanation that it was only an estimate.
I am not satisfied the BOQ contained the agreed price. Claimant was not able to say who authored the BOQ. Claimant was not able to
say the Minister’s verbal agreement put the price at $3,023, 200.00.00. I do not know why I should connect the BOQ to the Minister’s verbal agreement and his two subsequent letters. Claimant should
have summoned the author of the BOQ to explain what it was. I do not know what it is and cannot connect it to the Minister’s
verbal agreement and the two subsequent letters, unless the Minister himself does that in evidence. If I do I will be making the
verbal agreement, myself. The current PS, an expert himself, says in evidence, a BOQ is only an estimate for a project.
- Claimant was not able to satisfy the Court that the work was done and independently certified to be completed by the supervising
engineers. The context here does not accommodate the ratio decidendi in Lebaro to the benefit of the claimant. There is no written contract to start with. If there is anything to go by in Lebaro, it
is that, there must be a written contract for every contract that the state enters into with service providers. With a written contract it means all the financial instructions and tendering requirements were satisfied. Hence a valid, binding
and a legally enforceable contractual relationship would exist between the service provider and the state. The current PS says in evidence that a contract is valid if five things are present – Tender dossier containing tender instructions to tenderers; Special conditions of contract; Drawings; Specifications and Written Contract.
According to this uncontested evidence, the written contract comes at the end of the process. Not the other way round as what we have
seen with the Minister’s verbal agreement.
- Without a written contract, it means all the financial instructions and tendering requirements were not satisfied. Hence no valid,
binding and legally enforceable contract was entered into. The worst case is verbal contracts. One cannot certainly have a valid,
binding and legally enforceable contract with the state verbally. And if I may add: Contract for service provision to the government, such as construction of bridges, roads, wharfs etc is governed by well-defined contractual
process of competitive bidding that seeks to protect the public against the squandering of public funds and prevent abuse such as
fraud, favouritism and extravagance[5]. This is why we have the governing instruments such as tendering and financial instruction requirements. The Minister was well aware
of the well-defined contractual process of competitive bidding and financial instruction requirements, as seen in his letter of 15/03/2013, where he relevantly stated: -
- “This note therefore carries my instructions that you are to immediately pursue the required formalities with the appropriate
tender board, to offer the award to LB construction which is currently undertaking re-construction of the said road. I would appreciate
the assistance of the financial controller to this process to ensure the applicable financial instructions are comfortably met.”
(Underlined my own emphasis).
- The Minister’s letter was not the offer. For he says the appropriate tender board will offer the award to the company. That
contradicts the preceding paragraph where the Minister stated that he had verbally offered and awarded the work to the company. Again
there is no certainty as to the major terms of the contract because it was only a verbal agreement. But with the letters, it now
became partly written and partly oral agreement. Yet the major terms cannot be ascertained from the partly written contract or the
oral contract. And so claimant has to connect the major term on price to the BOQ. But the BOQ did not bring certainty as to price.
It was only an estimate for 3.5 Km of road not 2.5 Km. Mr. Wanefalea cannot amend the BOQ to say it was a typing error. He was not
the author. He should have called the author to establish typing error. Claimant did not provide evidence that the company completed
the work. There was no certificate to verify that the work was completed. What claimant relied on as Certificate of Completion at
page 16 of TB, was not certified by the responsible PS – Mr. Lomu. Hence Court cannot be satisfied that the company completed
the road.
- I will therefore answer the issues posed for trial in paragraph 7 as follows: -
- (i) There is no written contract. So I cannot be satisfied that the price (consideration) was $3,023,200.00. What is taken as contract price in the BOQ is not the contract price. I do not know who the author of the BOQ is. Mr. Wanefalea
tried to amend the BOQ saying there was a typing error. Should be 2.5 Km of road and not 3.5 Km. If it is 2.5 Km then certainly the
price should be below what is quoted in the BOQ as $3,023,200.00, for 3.5 Km.
- (ii) There is no evidence before me that MID had assessed the contract amount because there was no written contract. If there was
a written contract the contract price would have been prior assessed and included as the most crucial term of the contract. Like
I found above there is no certainty about the contract price.
- (iii) The contract amount of $3,023,200.00 in the BOQ may be a guide. But a guide to what, I do not know. I do not know who the author was and how it has been pulled to become
a term of the verbal agreement. According to Wanefalea’s oral evidence he says having spoken to PS Lomu, PS Lomu told him the
job was not budgeted for. The current PS evidence that the MA did not initiate this job supports Wanefale’s otherwise, hearsay
evidence. So such evidence is admissible. The amount of $3,023,200.00 in the BOQ is an estimate for the works shown in there. It is an estimate for 3.5 Km not 2.5 Km.
- (iv) There is no valid contract. So you cannot say the MID and or MA were trying to avoid their obligations under the contract. Obligations
like assessing the contract amount and failing to obtain the endorsement of the Minister of MID. The contract was not initiated by
the MA. So every requirement that should normally be activated prior to award including competitive bidding were not complied with.
And the Minister has no legal authority to make verbal agreement for award of service contracts on behalf of the state. Award of
public contracts for the government has well defined contractual requirements (repeat and reaffirm paragraphs 23 and 24).
- (v) The verbal contract was void and unenforceable. The Minister lacks authority to make verbal contracts for the MA. The government
was not aware of the contract and had not budgeted for it. And so you cannot say that responsible officers have failed to adhere
to the necessary tendering and financial instruction requirements. The Ministry did not initiate the project. So how could the officials have put in place the necessary preparations
in terms of the compliance to requirements such as the award of the contract to be made by CTB? Mr. Wanefalea knew about this requirement.
But he took the Minister’s words as final and absolute? May be I should make it clear to all that the Minister of every Ministries
do not have power to make verbal contracts for service providers to government Ministries.
- (vi) The principle in Lebaro is not applicable to assist the claimant in the context here, where there was no written contract to start with.
- (vii) The verbal agreement by the Minister is null and void and is unenforceable. Hence cannot bind the state. The Minister has no
authority to make a verbal contract on behalf of the MA. There was no valid contract. Hence the non-compliance with the public tendering
and financial instructions requirements.
- (viii) I am not certain on the waiver in view of the emergency, because only a written contract would have make certain, things like
waiver. Where there is no written contract to start with, I cannot be satisfied with urgency and waiver. If there was a valid contract
to start with, things like urgency and waiver would have been agreed to. Mr. Wanefalea says an officer told him there will be waiver.
Mr. Wanefalea could not recall who that officer is. And that evidence is mostly hearsay not corroborated and is inadmissible.
- The claim is therefore dismissed in its entirety with cost.
THE COURT
JOHN A KENIAPISIA
PUISNE JUDGE
[1] See letter at page 24 – 25 of Trial Book (TB).
[2] Letter is at page 26 of TB.
[3] Whatever the Minister said, that Mr. Wanefalea referred to in evidence, is hearsay evidence, not admissible, unless corroborated.
[4] Lebaro v Attorney General [2016] SBHC 185; HCSI-CC 64 of 2016 (19th October 2016).
[5] https://legal-dictionary.the freedictionary.com/Public+Contract#:~:text=An agreement to perform a, to purchase goods and services.
PacLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.paclii.org/sb/cases/SBHC/2021/107.html