Home
| Databases
| WorldLII
| Search
| Feedback
High Court of Solomon Islands |
lass="MsoNormal" aal" align="center" style="text-align: center; margin-top: 1; margin-bottom: 1"> COURT OF SOLOMON ISLANDS
Civil Case No. 131 of 1996
WILLIAM RANan>
v
MELANESIAN HOLDINGS LIMITEIMITED
High Court of Solomon Islands
Before: Muria CJ.
Civil Case No. 131 of 1996
Hearing: 23 April 1999
Judgment: 30 April 1999
A. Nori for Plaintiff
. Radclyffee for Defendant
MURIA CJ:
The plaintiff's claims in this case are for damages for breach of contract, negligence and loss of income brought against the defendant. The claims arose out of the work done by the defendant on the plaintiff's vessel the “M. V. Higota” (“the Vessel”).
Brief background
ass="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> Facts not disputed
It is not in de that the Vessel was an old wooden one. While the ship p was at Taroniara, the plaintiff engaged two men from Langa Langa to do repair work on the body of the Vessel, They finished that work toward the end of 1992. Following that, the plaintiff requested the defendant to install the engine in the vessel and to do full body and all other engineering works on the Vessel. The plaintiff made payments for the work done on the vessel at the end of September 1993 and was told to check for delivery of the Vessel, the following month, October. The Vessel was not ready for delivery then and it was in February 1994 that the work on the Vessel was completed and was delivered to the plaintiff. It is also not disputed that the plaintiff had not yet paid for the work clone by the defendant on the Vessel between October 1993 and February 1994. The plaintiff took delivery of the Vessel in February 1994 and sailed to Honiara where it was said to have experienced mechanical problems shortly after it arrived.
On the undisputed facts as stated andhe light of the claims by t by the plaintiff, it seems to the Court that the issues to be determined in this case are:
1. Whether the alleged mechanical de did in fact occur.
<
2. Whether thendant was responsible for tfor those defects, if they did in fact occur.
3. Whether the plaintiff should pay the defendant on then the counter-claim or part of it.
These issues must be determined on the evidence before turt. There are other ther subsidiary issues also which the Court would need to consider, such as, the status of the Vessel and how that would affect the reasonableness and skill with which the defendant carried out their work on the Vessel; also whether those who operated the Vessel after its repair exercised due diligence and skill, in particular, when handling its engine. All these issues are important in determining whether the defendant should be held responsible for the faults subsequently experienced by the Vessel after it left the defendant's shipyard.
Whether there was a contract between the parties
When the plaintiff entered into the “Purchase Agreement” (Exh.1) with Mr. Gavin at Honiara on 26 July 1989, it is clear that the Vessel was already lying ashore at Taroniara. The Vessel was “delivered” to the defendant for engine fitting and other works to be done on it. The evidence shows that the defendant accepted to do the work requested by the plaintiff and they did do the works requested on the Vessel. The plaintiff paid the defendant for the work done on the ship up to September 1993. It was in February 1994 that the work on the ship was completed and the plaintiff took delivery of the Vessel. The costs of the work done on the Vessel between October 1993 and February 1994 had yet to be paid by the plaintiff.
lass="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> There was o evidence, a binding contract between the plaintiff and thed the defendant in this case. As agreed under that contract, the defendant installed the engine in the Vessel and did full body works on it. Before delivering it to the plaintiff, the defendant carried out tests called “Speed Trials” to see if the works on the Vessel were properly done. The “speed Trials” were successful and the Vessel was handed over to the plaintiff. That was the fulfilment of the contract for work on the part of the defendant and for which they have been partly paid.
lass="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> The Defects
It is the case for laintiff that there were defects in functioning of th the engine of the Vessel and that the defects were the result of the poor workmanship of the defendant. I do not think that there is evidence to dispute the fact that the engine experienced “hard start” while it was in Honiara. A letter dated 7 March, 1994 from the Licensing Section of the Ministry of Transport, Works & Utilities Exh. 2) confirmed this. In that letter which was written following a survey of the Vessel, it was noted that the engine starting system was defective and that there were electrical faults needed to be rectified. It would appear that these defects were attended to.
Sometime later the ship then made a trip to Honiara and on the wahe way, oil leakage was discovered from the engine. When the ship returned to Ysabel from Honiara from this trip, the engine stopped on arrival at Ysabel. The engine bearings seized - up. The plaintiff ordered spare parts through the defendant at the cost of $800.00. The spare parts arrived, but were wrong ones. The engine had not been fixed since then and the ship ceased operation since then.
The evidence show that there were faults in the l’s engine. These fau faults were found after the plaintiff took possession of the Vessel following its full overhaul by the defendant. The question is who is responsible for the defect? Were they the consequence of a poor workmanship of the defendant? It is to those considerations that I now turn.
The case for the plaintiff is that the defects were the result of the def defendant’s negligence or poor workmanship. In a contract such as the one in this case, for work to be done, one party (plaintiff) agreed to pay and the other, (defendant) agreed to do the work. Implied in that contractual relationship in this case, is that the defendant would carry out the work properly with reasonable care and skill as shipyard operator and that the plaintiff would pay for the work done. From the nature the business transaction between the parties, that must be the implication which could reasonably be inferred in this case. See The Moorcock (1889)14 P.D. 64; [1886 - 90] All E.R. Rep. 530; Reigate -v- Union Manufacturing Co. (Ramsbottom) [1918] 1 K.B. 592; Shirlaw v. Southern Foundries (1926) Ltd [1939] 2 K.B 227.
he plaintiff's witness Lonsdale Bosa checked the Vessel’s el’s engine in early 1994 at Ysabel and found the timing were misplaced. He fixed that and the engine was working again. It was after the second trip from Honiara to Ysabel that Mr. Bosa was asked to check the engine again. He did and found the gasket was in place except that it was a wrong one. This is in contrast to Mr. Tanisapa's evidence that there was no gasket present in the engine.
George Nigiso who gave evidence for the defendant was a qual qualified engineer who worked at the defendant’s shipyard for 20 years. He held a 300 HIP Engine Certificate. He certainly has had more years experience as engineer. He supervised the work on the plaintiff’s vessel and its engine was done competently and found no problem at all after it was completed and even during and after the trial runs or “speed trials.” The engine was an old one and despite that, the overhaul work on it was done competently. He agreed that there were apprentices who helped in the overhauling work, but he said those were under his supervision. According to him, the problem with oil leakage could only have (sic) happened if someone opened up that part of the engine which could cause the seal to break. In which case a new one had to be put in.
If therefore Mr. Tanisap no gasket in the engine and Mr. Bosa found later on r on that there was actually one in place, though wrong size, then the conclusion is that someone must have done something to the engine resulting in inserting a gasket in that part of the engine.
We are not told exactly when were the trips to aom Ysabel and how far apart were those trips from each other. The Court was only told that the first trip to Ysabel must have been in early 1994 which must be after 7th March i.e. after the Marine inspection in Honiara. The second trip must have been sometimes, late March or early April 1994 since in his letter of 4 May 1994 to the defendant's General Manager, the plaintiff was talking about being already out of business for six (6) weeks.
This case, however, concerns a contract the substance of which is the provision of service by the defendant, that is, the doing of the repair work or overhaul on the plaintiff's vessel. In such a contractual relationship, there must be the implied term that defendant would carry out the service with reasonable care and skill. The existence of such duty has been conceded (and in my view, rightly so) by the defendant in this case. It is however upon the plaintiff to establish that the work done on his vessel was done in breach of that duty. Regard must also be taken of the status of vessel. This was a vessel which was old and totally out of navigation. It was sold on “AS IS AS LIES” basis. Both the body and the engine of the vessel had had to be completely overhauled. It had been lying ashore for sometime and had not been in service for quite sometime. From the Purchase Agreement (Exh. 1) it would be safe to assume that the vessel must have been lying ashore at Taroniara even before 26 July 1989. Thus in a case such as this, I feel the status of the vessel together with the nature of the repair work and the whole nature of the work which the defendant contracted to do are important considerations in determining the reasonableness of the care and skill with which the defendants carried out their work. The burden is on the plaintiff to show that the status of the ship and the nature of the work to be done were such that when the defendants did what they contracted to do, they fell below the standard of workmanship required of them.
class="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> Regard muso be taken of the status of vessel. This was a vessel whic which was old and totally out of navigation. It was sold on “AS IS AS LIES” basis. Both the body and the engine of the vessel had had to be completely overhauled. It had been lying ashore for sometime and had not been in service for quite sometime. From the Purchase Agreement (Exh. 1) it would be safe to assume that the vessel must have been lying ashore at Taroniara even before 26 July 1989. Thus in a case such as this, I feel the status of the vessel together with the nature of the repair work and the whole nature of the work which the defendant contracted to do are important considerations in determining the reasonableness of the care and skill with which the defendants carried out their work. The burden is on the plaintiff to show that the status of the ship and the nature of the work to be done were such that when the defendants did what they contracted to do, they fell below that standard.
The evidence in this case, however, ijudgement, makes the positiosition very clear, that is to say, here was a vessel old and in a dilapidated condition, out of navigation and lying ashore, most likely even before the plaintiff purchased it; extensive body work had to be done on it; its old engine required major overhaul; having done repairs and other extensive work on it, the vessel was tested and became functioning; the plaintiff took delivery of it after it had gone through successful “speed trials” and sailed it to Honiara; the vessel was operated by bosun and an engineer who was then only less than three years qualified; all the defects said to have arisen from the vessel’s engine had only occurred after the vessel had been successfully tested and after the vessel was put in the charge of the plaintiff’s employees; there were inconsistencies in the detection of the defects, especially, with regard to the gasket, between the plaintiff’s engineer and Mr. Bosa who had more than 30 years’ experience in marine engineering; there is the strong inference from the evidence that the engine had been worked on after it left the defendants’ hands; and that the plaintiff failed to take the reasonable step, expected of him, of taking the vessel back to the defendants to attend to the faults, instead he allowed his own employed engineer and other people to deal with the faults. All these factors together with the status of the vessel itself bear out heavily a burden on the plaintiff of satisfying the Court that the defendants had not done their jobs with reasonable care and skill.
Conclusion
Unfortunately for the plaintiff, the evidence is such that the Court cannot be satisfied that the defendants could possibly be said to have carried out their jobs without reasonable care and skill. The contrary is very much the case. They had carried out the work as contracted to do and had done so with reasonable care and skill. I do not think it would be right to expect the defendant in this case to resurrect the plaintiff's old vessel into a 100% fault - free and seaworthiness. That being the case, the plaintiff's claim cannot succeed and is dismissed.
The plaintiff conceded that the defendant did fr work on the ship from m October 1993 to February 1994. That being so, the defendant must be paid for the work it did. On the other hand the defendants have not disputed that the plaintiff ordered spare parts to the value of $800.00 and those parts had not been used but were or are still in the possession of the defendant. I feel that amount must be deducted from the counter - claim amount.
There will be jut for the defendants in the Counter - claim in the sum of $14,056.69 less $800.00. The sum payable to the defendants is $13,256.69.
Order:
(1) Plaintiffs Claim is dismissed.
>
(2) Judgment for the defendants on the Counter-Cler-Claim in the sum of $13, 256.69 plus costs.
ass="MsoNoMsoNormal" align="center" style="text-align: center; margin-top: 1; margin-bottom: 1"> (GJB Muria)
CHIEF JUSTIJUSTICE
PacLII: Copyright Policy | Disclaimers | Privacy Policy | Feedback
URL: http://www.paclii.org/sb/cases/SBHC/1999/45.html