Home
| Databases
| WorldLII
| Search
| Feedback
Supreme Court of Guam |
IN THE SUPREME COURT OF GUAM
M ELECTRIC CORPORATION,
Plaintiff-Appellant,
v.
PHIL-GETS (GUAM) INTERNATIONAL TRADING CORPORATION dba
J&B MODERN TECH and CHUNG KUO INSURANCE COMPANY
LTD.,
Defendant-Appellees.
Supreme Court Case No.: CVA15-013
Superior Court Case No.:
CV1423-10
OPINION
Filed: December 28, 2016
Cite as: 2016 Guam 35
Appeal from the Superior Court of Guam
Argued and submitted
on February 22, 2016
Hagåtña, Guam
Appearing for Plaintiff-Appellant:
Thomas M. Tarpley, Esq. Thomas McKee Tarpley Law Firm 414 W. Soledad Ave., Ste. 904 Hagåtña, GU 96910 |
Appearing for Defendant-Appellee:
Seth Forman, Esq. Dooley Roberts & Fowler LLP 865 S. Marine Corps Dr., Ste. 201 Tamuning, GU 96913 |
BEFORE: ROBERT J. TORRES, Chief Justice; F. PHILIP CARBULLIDO, Associate Justice; KATHERINE A. MARAMAN, Associate Justice.
CARBULLIDO, J.:
[1] Plaintiff-Appellant M Electric
Corporation (“MEC”) appeals from a final judgment entered in favor
of Defendant-Appellees
Phil-Gets (Guam) International Trading Corporation d/b/a
J&B Modern Tech, and Chung Kuo Insurance Company, Ltd. (“Chung
Kuo”) (collectively, “J&B”). MEC argues that the trial
court (1) abused its discretion in denying its request
for Leave to File Amended
Complaint (“motion to amend”) to include a claim for compensable
overtime costs (“overtime
claim”), (2) erred in finding that its
claim for equipment standby costs (“standby claim”) was barred by a
“no
damage for delay” (“NDFD”) contract provision, and
(3) erred in dismissing its claim for additional excavation
expenses
(“excavation claim”).
[2] J&B argues that the judgment
should be affirmed because (1) the Supreme Court of Guam does not have
jurisdiction over the denial
of MEC’s motion to amend or, in the
alternative, the trial court’s decision was not an abuse of discretion,
(2) the NDFD
clause is valid and relevant exceptions do not apply, and (3) the
terms of the Subcontracts bar MEC’s excavation claim. J&B
also raises
the issue of whether the overtime claim is time barred as to Defendant-Appellee
Chung Kuo by arguing that MEC failed
to present any evidence concerning Chung
Kuo, and failed to bring suit on the overtime claim against Chung Kuo within the
applicable
one-year deadline. MEC responds by arguing that Chung Kuo is jointly
and severally liable by the terms of 5 GCA § 5304 as a
surety of
J&B’s bond obligations.
[3] We hold that this court has
appellate jurisdiction, that the trial court abused its discretion when denying
the motion to amend,
that the overtime claim is not time-barred with respect to
Chung Kuo, that NDFD clauses stated in the contracts at issue cover the
type of
delays incurred by MEC but further findings are required to determine whether an
exception to the NDFD clauses applies, and
that the trial court did not err in
denying MEC’s excavation claim. For the reasons detailed herein, we
affirm in part, reverse
in part, and remand for further proceedings not
inconsistent with this opinion.
I. FACTUAL AND PROCEDURAL BACKGROUND
A. Procedural Background
[4] MEC initiated the
underlying action by filing its Complaint for Declaratory Relief and Money Owed
on Construction Project. J&B
answered and moved for summary judgment. The
trial court entered judgment in favor of J&B upon its Motion for Summary
Judgment.
MEC filed its first appeal.
[5] Upon review, this court
reversed the trial court’s grant of summary judgment and remanded the case
for further proceedings.
M Elec. Corp. v. Phil-Gets (Guam) Int’l
Trading Corp. (“M Elec. I”), 2012 Guam 23 ¶
50.
[6] On remand, MEC requested leave to amend its Complaint. After
accepting opposition and reply briefs, the trial court denied MEC’s
request. After a bench trial, the trial court entered judgment on the merits in
favor of J&B. MEC timely filed its second appeal
in this matter.
B. Factual Background
[7] Guam Power Authority (“GPA”)
hired J&B under construction contracts (“Contracts”) to perform
work on
two underground power line conversion projects (collectively,
“Projects”). The first was to convert power lines from
the Macheche
Substation to the Guam International Airport Authority (“GIAA”).
The second was to convert power lines
from Macheche Substation to Harmon
Substation to San Vitores existing electrical manhole (“San
Vitores”). J&B hired
MEC as a subcontractor to “provide labor,
equipment, and materials to excavate, install underground pipes, and restore
excavated
areas and roads.” M Elec. I, 2012 Guam 23 ¶
3.
[8] GPA held a pre-bid conference prior to awarding the Contracts
to J&B. An engineering manager for GPA, Joven Acosta, testified
that he
informed bidders at the pre-bid conference that delays obtaining permits from
the Guam Department of Public Works (“DPW”)
should be expected. He
also testified that he informed bidders to increase their bids to account for
delay-related costs because
“getting the permits from DPW [would] be a
challenge.” See Transcripts (“Tr.”) at 31 (Bench
Trial, Nov. 13, 2014).
[9] Generoso Bangayan, J&B’s
president, testified that he was present at the pre-bid conference and heard
Acosta’s comments.
Acosta’s comments were not reflected in writing
in any of the contracts or related documents.
[10] Noel Lomtong,
MEC’s project engineer on the Projects, testified that he and Carlos Nunez
were present for the pre-bid conference.
The sign-in sheet for the pre-bid
conference showed the names of both men and listed their company of affiliation
as “M Electric.”
Def.’s Ex. I (Sign In Sheet for Pre-Bid
Conference Bid No. GPA-020-07), M Elec. Corp. v. Phil-Gets (Guam) Int’l
Trading
Corp., CV1423-10. The contact number listed for Nunez was MEC’s
phone number.
[11] MEC’s president and general manager, Marcelo
Moises, testified that Nunez was an MEC employee at the time of the pre-bid
conference
but Lomtong was not. He also testified that Nunez was simultaneously
employed as a project manager with DA-RI Trenchless (“DA-RI”),
a
Philippine company. He testified that MEC was not involved in the Projects at
the time of the pre-bid conference because it was
not capable of performing the
horizontal drilling originally required by J&B. The trial court was not
persuaded that Nunez and
Lomtong did not attend the pre-bid conference as
representatives of MEC.
[12] MEC began working with J&B on the
Projects after the pre-bid conference when J&B accepted MEC’s written
job proposals.
J&B accepted and signed the proposals for each of the
Projects and drafted corresponding subcontracts (“Subcontracts”).
Moises signed the Subcontracts and initialed each page. This court held
in M Electric I that the Subcontracts were supported by consideration and
binding on the parties.
[13] The Subcontracts both contained
“time of the essence” (“TOE”) clauses. The GIAA
Subcontract read: “The
Subcontractor shall substantially complete the Work
to the satisfaction of the Contractor and the Owner on or before December 20,
2008. Time shall be of the essence in the Subcontractor’s performance of
this Agreement.” Record on Appeal (“RA”),
tab 15, Ex. A at 2
(Subcontract Agreement, Mar. 24, 2008). The San Vitores Subcontract contained a
nearly identical clause, modifying
only the completion date, January 13, 2009.
RA, tab 15, Ex. B at 2 (Subcontract Agreement, Apr. 16,
2008).
[14] The Subcontracts and prime Contracts each contained NDFD
clauses. The Subcontract NDFD clauses provided for extension of time as
the
exclusive remedy available to MEC for delays caused by J&B. The NDFD
clauses required a written claim “within five
. . . days from the
inception of such delay.” RA, tab 15, Ex. A at 2 (Subcontract Agreement,
Mar. 24, 2008); RA, tab 15, Ex.
B at 2 (Subcontract Agreement, Apr. 16, 2008).
The prime Contracts between GPA and J&B contained a general NDFD clause
which
stated that “[n]o extended overhead costs or standby costs shall be
awarded/granted as a result of delays from the Civil work.”
Def.’s
Ex. C at SP-2 (Special Provisions, San Vitores Contract), M Elec. Corp. v.
Phil-Gets (Guam) Int’l Trading Corp.,
CV1423-10. The Subcontracts
contained “Changes to Plans” provisions, requiring a written, signed
order prior to any
work performed that differed from that described by the
agreements and stating that “the Contractor shall be under no obligation
to pay for . . . unauthorized work.” RA, tab 15, Ex. A at 2-3
(Subcontract Agreement, Mar. 24, 2008); RA, tab 15, Ex. B at 2-3 (Subcontract
Agreement, Apr. 16, 2008).
[15] At numerous times during performance
of work under the Subcontracts, MEC experienced delays based on not being able
to obtain the
necessary permits from the Department of Public Works
(“DPW”). Lomtong testified that no change order was made until
the
Projects were completed. Tr. at 85 (Bench Trial, Nov. 5, 2014) (“No,
because they told us that . . . we have to do the
other change order until [sic]
. . . the project was done.”). The vice-president of J&B, Nelia
Bangayan, testified that
upon completion of the Projects, J&B paid MEC the
full contract amount. GPA did not pursue liquidated damages for the delays.
Acosta testified at trial that GPA did not assess damages against J&B
because the company understood that obtaining highway
encroachment permits from
DPW would be difficult and inclement weather was to be
expected.
[16] J&B moved for summary judgment, arguing that the
plain and unambiguous terms of the Contracts and Subcontracts barred MEC’s
claims. MEC opposed J&B’s motion, arguing that the Subcontracts were
not legally binding. The trial court entered judgment
in favor of J&B upon
its Motion for Summary Judgment in March 2012 (“March 2012
Judgment”).
PacLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.paclii.org/gu/cases/GUSC/2016/35.html