Home
| Databases
| WorldLII
| Search
| Feedback
Supreme Court of Guam |
IN THE SUPREME COURT OF GUAM
TANAGUCHI-RUTH
+ ASSOCIATES
dba TANAGUCHI-RUTH
ARCHITECTS,
Plaintiff-Appellee,
v.
MDI
GUAM CORPORATION dba LEO PALACE
RESORT,
Defendant-Appellant.
OPINION
Filed:
April 1, 2005
Cite as: 2005 Guam
7
Supreme Court Case No.: CVA03-021
Superior Court Case No.:
CV0671-02
Appeal from the Superior Court of Guam
Argued and submitted
on October 15, 2004
Hagåtña, Guam
Appearing for Plaintiff-Appellee: Duncan G. McCully, Esq. McCully & Beggs, P.C. Ste. 200, 139 Murray Blvd. Hagåtña, GU 96910 |
Appearing for Defendant-Appellant: Thomas L. Roberts, Esq. Dooley, Roberts & Fowler LLP Ste. 201 Orlean Pac. Plaza. 865 S. Marine Dr. Tamuning, Guam 96911
|
BEFORE: F. PHILIP CARBULLIDO,
Chief Justice; FRANCES M. TYDINGCO-GATEWOOD, Associate Justice; ROBERT J.
TORRES, JR., Associate Justice.
TORRES,
J.:
[1] The
Defendant-Appellant, MDI Corporation dba Leo Palace Resort
(ALeo Palace"),
appeals a judgment awarding quantum meruit
recovery to the Plaintiff-Appellee, Tanaguchi-Ruth + Associates dba
Tanaguchi-Ruth Architects
(ATRA"), for
architectural work performed by TRA on behalf of Leo Palace. Leo Palace's
primary contention on appeal is that the trial
court erred in allowing recovery
because Leo Palace did not receive or use TRA's work, and, therefore, Leo Palace
did not receive
a benefit from TRA as required for recovery under a
quantum meruit theory. Leo Palace also
challenges the trial court's finding that TRA satisfied its duty to mitigate
damages, and finally, challenges
the trial court's award of prejudgment
interest. We hold that the trial court correctly allowed for
quantum meruit recovery, but erred in
awarding recovery for work performed after TRA became reasonably aware that it
could not perform the work
within Leo Palace's design budget. We further
determine that Leo Palace waived its objection to the trial court's award of
prejudgment
interest. We affirm the lower court's judgment in part and reverse
in part.
I.
[2] The
construction project for the Leo Palace Resort Complex in the Manenggon Hills
area of Yona commenced in the 1980's. In the late
1980's, TRA was hired by and
performed architectural services for Leo Palace for portions of the project.
After construction commenced
on the project, in the early 1990's, Leo Palace
decided to indefinitely postpone the interior finishing of the hotel building
(now
the Hotel Belvedere) on the Complex. The hotel sat as a shell until
November of 2000, at which time Leo Palace decided to complete
the interior
work.
[3] In late 2000,
Sumitomo Construction Company contacted and informed TRA that Sumitomo was
chosen as the contractor for the construction
of the hotel. TRA understood that
its role was to take design concepts from other architects hired by Leo Palace
and to prepare the
construction drawings and specifications to obtain the
necessary Guam building permits. TRA began initial preparations, deciding
to
complete their work in three staggered packages, which would enable the permits
to be acquired in stages. Package 1 entailed converting
TRA's early drawings
into Computer Assisted Drafting format, and designing the guest rooms. Package 2
covered the common areas and
lobbies, while Package 3 encompassed the hotel's
restaurants.
[4] As originally
planned, TRA's fee was to be submitted to Sumitomo, included as part of
Sumitomo's total construction costs and be
paid for by Sumitomo. TRA submitted
to Sumitomo an initial fee proposal for all three packages for $1,285,900.00.
Sumitomo found
this amount problematic for unstated reasons, and informed TRA
that Sumitomo would negotiate a new amount and thereafter submit what
they
considered an acceptable fee proposal to Leo Palace. TRA and Sumitomo never
decided on any set amount for the work for the three
packages.
[5] TRA eventually
came to an agreement with Sumitomo that Sumitomo would guarantee to pay TRA's
fees for the Package 1 work. TRA then
started work on the Package 1 documents.
At some point after TRA started work on Package 1, Leo Palace arranged to pay
TRA directly
for that portion of the work. During this time, TRA's fee for the
Package 1 work was still not made definite.
[6] On July 7, 2001, two
representatives of Leo Palace, Mr. Ishii and Mr. Hyodo, met with TRA's
representative, Mr. Ruth, to negotiate
the fee for the Package 1 work, which at
that point was approximately 60% completed. The parties reached an agreement on
the fee
and Leo Palace instructed TRA to complete the Package 1 work, which was
due on July 31,
2001.[1]
At the July 7, 2001 meeting, Mr. Ishii also requested that TRA submit a quote
for the Package 2 work. Up until this point, TRA had
been working and
corresponding with two architectural firms hired by Leo Palace regarding the
scope and ideas for the Package 2 work.
These firms were Archiprime
(AAP") and Riccardo
Tossani Architecture Co.
(ARTA").
[7] On
July 24, 2001, Leo Palace sent TRA a letter, addressed to Mr. Ruth, informing
TRA that Sumitomo was to arrange for RTA and TRA
Ato continue with the
application of a building permit for the (phase one) guestrooms." Appellant's
Excerpts of Record
(AER"), p. 72 (Letter
from Abe to TRA of 7/24/01). The letter further stated:
However, development of the project has increased at such a rapid rate, therefore it is getting steadily harder (for the above RTA and AP companies) to carry on working together on and after phase two. Kanko Kikaku Sekkeisha Co. (KKS) . . . has been chosen to continue and complete the project. The operating arrangement has been concluded and is now contracted to KKS.
KKS would like to continue the project with the guidance of TRA as a local partner, Leopalace . . . has approved of this move without any obligations, and we would appreciate your continuing support of the project. The construction period has a prearranged time limit, therefore, we are theorizing as to apply the original drawings and specifications (of the almost completed phase one) in order to prevent further delays. Please note that KKS will be making use of your preliminary drawings.
We would be grateful if the estimate and invoice could be submitted to the office of Leopalace . . ., situated at MDI GUAM CORPORATION, however this must be sent through the services of KKS.
We would highly appreciate your cooperation in the development of Manenggon Hills and the collaborating local Guam companies.
/s/ Satoshi Abe
Director
Appellant's
ER, p. 72 (Letter from Abe to TRA of
7/24/01).
[8] Upon receipt of
the July 24, 2001 letter, TRA thereafter commenced work on Packages 2 and 3,
apparently under the direction of KKS.
Specifically, KKS submitted its
conceptual drawings to TRA on September 20, 2001, and requested that TRA
complete various items of
work utilizing these drawings. At this point the
deadline for the completion of the Package 2 and 3 work was October 31, 2001.
This
deadline reflected the November 1, 2001 deadline for applying for the
building permits. Considering these deadlines, upon receipt
of KKS's drawings on
September 20, 2001, TRA enlisted the help of engineering consultants to work on
Packages 2 and 3 while it simultaneously
prepared its fee proposal for these
packages. The consultants included GK2 Inc., EMC2 Mechanical, Inc., and EMCE,
Consulting Engineers.
On September 28, 2001, TRA sent Leo Palace its fee
proposal for Packages 2 and 3. The proposed fee was $827,000.00. At this point,
TRA had incurred $26,050.00 in fees for work already performed on Packages 2 and
3, which included work done by both TRA and its
engineering
consultants.
[9] On October 10,
2001, a representative of KKS left a message with TRA recommending that Mr. Ruth
meet with Mr. Ishii on the following
Saturday regarding Leo Palace's concerns
with TRA's fee proposal. The KKS representative also recommended that TRA call
Mr. Ishii
prior to Mr. Ishii's arrival on Guam. TRA did not call Mr. Ishii.
Notwithstanding this communication by KKS to TRA regarding the
concerns over
TRA's fee proposal, KKS, on October 11, 2001, sent an email to TRA indicating
that Leo Palace had
Aaccept[ed] to proceed
design work based on the original design in order to preserve the permit
schedule." Appellee's Supp. Excerpts
of Record
(ASER"), p. 44 (E-mail
from Yukiharu, Architect, KKS to H. Mark Ruth, FAIA and Melet Santos, TRA (Oct.
26, 2001, 9:00 pm)). KKS further
instructed TRA to proceed with the layout
revisions to the car parking.
[10] Mr. Ruth, Mr. Ishii and
Mr. Hyodo met on October 15, 2001. At the meeting, Mr. Ishii informed TRA that
Leo Palace's budget for the
Package 2 and 3 work was between $300,000.00 and
$400,000.00. Mr. Ruth knew at this meeting that TRA could not possibly do the
work
required for $300,000.00 to $400,000.00, but did not disclose this
information to Mr. Ishii or Mr.
Hyodo.
[11] On October 18, 2001,
TRA faxed Leo Palace a proposed new fee of $659,000.00. Mr. Ruth, Ishii, and
Hyodo met later that day, and Mr.
Ishii again informed Mr. Ruth that Leo Palace
could not pay more than between $300,000.00 and $400,000.00.
[12] Mr. Ruth sent a letter to
Leo Palace on October 22, 2001, revising and reducing TRA's fee to $592,000.00.
Mr. Ruth also informed
Leo Palace that the work for Package 2 was 70% complete
for the architectural and structural portions, and 50% complete for the
mechanical
and electrical portions. Mr. Ruth also stated that they did not want
to be responsible for any schedule delays, and that
A[a]s required by the
schedule, these documents will be complete November 1st. Please advise us in
writing if this is not what you
wish." Appellant's ER, p. 88 (Letter from TRA to
Ishii of 10/22/01).
[13] On
October 23, 2001, Mr. Ishii faxed a letter to Mr. Ruth, stating that they
received the revised estimated design fee for Packages
2 and 3. The letter
continued: AHowever,
we regret to say that we are not able to accept your proposal because the Amount
is still too high than our budget. Therefore,
we herewith inform you not to
order the job to your firm this time." Appellant's ER, p. 126 (Letter from Ishii
to TRA of 10/23/01).
[14] Leo
Palace eventually hired another local architecture firm Martin, Cristobal &
Laguana (AMCL") to do
the Package 2 and 3 work for a negotiated fee of between $320,000.00 and
$330,000.00.
[15]
PacLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.paclii.org/gu/cases/GUSC/2005/7.html