Home
| Databases
| WorldLII
| Search
| Feedback
Fiji Law Reports |
IN THE COURT OF APPEAL OF FIJI
BARAM SEN
v
GOVIND SWAMY NAIDU & ANOR
[COURT OF APPEAL (Marsack, J. A., Henry, J. A., Spring J. A.)
7, 29 March 1979]
Civil Jurisdiction
Contract – Award of damages – liquidated sum fixed - plaintiff
may not recover that sum plus a further sum for actual
loss.
R. D. Patel for Appellant
G. P.
Shankar for Respondent
The appeal arose out of a building
contract.
The facts need not be recited. They are set out in detail
in the judgment. The contract had fixed the “liquidated and ascertained
damages” for delay in completion of the contract. A question arose as to
whether, if actual damages suffered were greater than
the amount fixed by the
contract, the injured party was entitled to recover a greater
sum.
The Court concluded that in such circumstances, a plaintiff
could not recover both the liquidated damages and also a sum concerning
the
actual loss sustained. The principle was that in the case of a sum fixed for
liquidated damages, plaintiff may recover that precise
amount only. The court
reduced an amount awarded accordingly.
See also discussion as to
Judges, discretion on costs. In this case the learned judge failed to exercise
his discretion correctly.
Cases referred to:
Cellulose Acetate Silk Co. v. Widnes Foundry (1933) A.C. 20.
Civil Service Co - operative Society Limited v. General Steam Navigation Limited (1903) 2 K.B. 756.
Ritter v Godfrey (1920) 2 K.B. 47.
MARSACK
J.A:
JUDGMENT
In this case the appeal and the cross appeal are against a judgment
of the Supreme Court delivered at Lautoka on the 3rd July 1978
which decided issues arising from a contract entered into between the parties
whereby the appellant, a builder, agreed
to erect a house for the respondents
upon the terms set out in the written contract.
The basic facts are
not materially in dispute. On the 26 June 1974 the parties signed an agreement
whereby the appellant contracted
to erect “a dwelling and its
appurtenances” on land belonging to the respondents at Nadi. The
specifications attached
to the contract were prepared by a draughtsman and were
set out in great detail. The total price was fixed at $30,900, and Clause
II in
the contract laid down provided inter alia that the work was to
be “fully completed” by the 15th December 1974; and
fixed $10 a day as liquidated damages for any delay beyond that date. However
the certificate of completion
and permit to occupy was not issued by the
building surveyor of the Nadi Town Council until 26 March 1975.
In
the Supreme Court the appellant took action against the respondent claiming
moneys due under the contract amounting to, $6,740.
This ,was made up of the
balance of the contract price still unpaid, plus a sum of $1,420 for
“extra work”, that is to
say, work beyond what was specified in the
contract but which was ordered by the respondents. The respondents counter
– claimed
for defective workmanship which they alleged appellant would not
repair and which would cost them $4,563.74 to have rectified by
other
contractors. They also claimed damages at $10 a day as provided in Clause 5 of
the contract, in respect of the delay in completion,
and loss of earnings for
the same period at $350 a month.
In his judgment the learned trial
judge held that two items claimed by the appellant as extra work, and charged up
for a total of
$520, could not be allowed as they were really covered by the
terms of the contact; but two items each of $450, for a double concrete
driveway
and the substitution of galvanised for wooden pipes, lay outside the contract
and were properly chargeable to the respondents.
In allowing this the learned
trial judge held that clause 12 of the agreement, which provided that no extra
work to be done except
with the written consent of the respondent, had been
waived by them. The $520 disallowed by the learned judge reduced the
appellant’s
claim to $6220, to which he was held to be entitled, less any
sum allowed on the counter claim.
With regard to the counter -
claim the learned judge allowed a total of $630 in respect of the defective
workmanship, and for the
delay in completion $1,890, being $930 under Clause 5
(93 days at $10 a day) and $960 for loss of rent. The deductions so allowed
totalled, $2,520, thus reducing the amount due to the appellant from $6,220 to
$3,700; and judgment was given in favour of the appellants
for this amount
without costs.
The grounds of appeal lodged by the appellant may be
summarised thus:
(1) That the learned trial judge was in error in holding that the appellant was liable for 93 days’ delay in completion of the building;
(2) That in any event the learned judge was wrong in allowing both $930 as liquidated damages, and $960 as loss of rent, for the period of the delay;
(3) That the learned judge erred in disallowing a sum of $520 in respect of the claim for extra work;
(4) That the learned judge erred in deducting from the contract price a sum of $630, for defective workmanship;
(5) That as the appellant had substantially succeeded in the Supreme Court he
should not have been deprived of his costs.
With regard to the
first ground; Clause 5 of the written contract provides that if the work be not
completed by the 15 December 1974,
“the Contractor shall pay or allow to the Owner a sum computed at the
rate of $10.00 per day as liquidated and ascertained damages
for delay, provided
however that if the work be delayed by force majeure or by reason of
exceptionally inclement weather or of authorised
extras or additions or strikes
or lock – outs a fair or reasonable extension of time shall be allowed, if
the Contractor shall
without delay expressly in writing request an
extension.”
It is common ground that no written request for
an extension of time was made by the appellant. Moreover, though evidence was
given
of some rainy days during the currency of the contract, there is no
suggestion that the weather could have been considered as exceptionally
inclement for that season. No other explanation was put forward to show that the
admitted delay in completion of the building contract
was justified to the
extent that the provisions of Clause 5 would not apply. The learned trial judge
allowed eight extra days in
respect of the time required for the construction of
the double concrete driveway which was not included under the contract, but
which was constructed by the appellant at the request of the respondents. This,
in our opinion, was reasonable. The question of the
actual period of the delay,
held by the learned trial judge to be 93 days, is dealt with later in this
judgment. In the result, nothing
has been shown to establish the
appellant’s exemption from liability for a delay of 93 days, with the
consequence as set out
in Clause 5. This ground of appeal accordingly
fails.
The second ground of appeal must, in our view, succeed. In
the written contract, the parties fixed the “liquidated and ascertained
damages” for delay in the completion of the contract. As is said
in Mayne on Damages, 11th Ed. p.
157:
“Where the sum consists of liquidated damages for breach of the
agreement, fixed and agreed upon between parties, that sum is
the ascertained
damage.”
The mere fact that the actual damage suffered is
greater than the amount fixed by the contract does not entitle the injured party
to recover a greater sum: Cellulose Acetate Silk Co. v.
Widnes Foundry (1933) A. C 20. It is true that in some
cases it has been held that a plaintiff could recover more than the amount fixed
in the contract as a penalty;
but in no case that we have been able to find has
it been held that a plaintiff could recover both the liquidated damages and also
a sum covering the actual loss sustained. The principle is that in the case of a
sum fixed as liquidated damages, a plaintiff may
recover that precise amount. We
therefore reduce the amount allowed under this head from $1,890 to
$930.
As to the third ground: the learned trial judge found that
the two items in respect of which $520 was claimed could not properly be
regarded as extras. He said:
“I am satisfied that they are provided for in the
contract.”
With respect we are unable to agree that these two
items were provided for in the contract. In the, course of his evidence the
appellant
stated:
“Owners wanted to change tiles to designed tiles. We agreed on $450.
Also wallboard from plain masonite to designed board. The difference was
agreed on as $70.”
Respondent Govind Swami Naidu gave,
evidence in the following terms:
“Plaintiff showed me some very inferior types of tile. I did not agree to tiles he selected.
I went and selected tiles myself. I gave samples of my selection to plaintiff.
He ordered tiles I selected.
“He did not say I would have to pay extra for them;
I did not tell plaintiff to put in designed wall boards instead of plain boards.
There are twelve designed boards in the house.”
Later in
the course of his cross - examination this respondent said:
“Specifications provided for Vinylflex floor tiles - I don’t know whether they were plain or designed tiles.
The ones in use in my home are designed tiles.
I brought samples of tiles. I marked and gave items to him.
I did not ask for change in tiles nor did I agree to pay, the difference in price.
Yes. Wall boards in specifications were plain, whereas plaintiff put in
designed boards done not at my request.”
In the
specifications Clause 9 provides that at the final adjustment, prime cost
vouchers or receipts must be available for inspection
so that, the contract sum
may be adjusted in accordance with the amounts actually expended. A schedule of
prime cost items set out
in the specifications provides for floor tiles in the
following terms:
"1" × "1" Unglazed tiles provided to
the floor of W.C.’s and shower $0.50 cents sheets
Vinylflex floor tiles 9´´ × 9´´ provided to
The 1st and ground
floor
$2.10 sq. yd.”
In exhibit 8 the contractor
sets out the actual cost of the designed tiles chosen by the owner as $799.22;
whereas the total cost
if the original tiles specified had been used would have
amounted to $350.53. the difference as shown is $448.69 and this according
to
the appellant’s evidence was agreed upon at the round figure of $450.
Further, in the same exhibit are figures showing the
difference between the cost
of the designed wall boards actually installed and those provided for in the
specifications, the additional
cost amounting to $70. The total additional cost
in respect of the tiles and the designed wall board thus amounts to $520 as
claimed.
No argument was put forward at the hearing of the appeal as to the
unreasonableness or otherwise of this figure.
In all we are
satisfied on the evidence that the designed tiles and wall boards used in the
completing of the house were of superior
quality to those described in the
specifications; and that therefore they could not properly be described as
“provided for
in the contract”. Clause 9 of the specifications
provides that there may be an adjustment of the contract sum in accordance
with
the amounts actually expended. That being so, we find that the sum of $520
should not have been deducted from the appellant’s
claim as was done in
the judgment of the learned trial judge.
With regard to the fourth
ground: there was ample evidence, accepted for what appears good reason by the
learned trial judge, establishing
the fact that the workmanship had been
defective to the extent shown in the particulars set out. Nothing was put before
this Court
to show that there had been, in fact, no such defective workmanship;
and it must be held to have been fully proved. There is accordingly
no merit in
this ground of appeal.
As to the fifth ground relating to the
question of costs: for the reasons which follow, we cannot, with respect, accept
the learned
trial judge’s decision. The appellant was forced to sue the
respondents for moneys which he claimed they were wrongfully retaining
and, as
it transpires, he was right so to do; as the appellant was substantially
successful before the Supreme Court. The Court has
an absolute and unfettered
discretion to award or not to award costs: Halsbury’s
Laws of England 3rd Edn. Vol. 30 para. 795
p.421.
The principle relating to costs was enunciated by Lord
Sterndale M. R. in Ritter v. Godfrey (1920) 2 K.B. 47 at p. 52
where he said:
“But there is such a settled practice of the courts that in the absence
of special circumstances a successful litigant should
receive his costs, that it
is necessary to show some ground for exercising a discretion by refusing an
order which would give them
to him. The discretion must be judicially exercised,
and therefore there must be some grounds for its exercise, for a discretion
exercised on no grounds cannot be judicial. If, however, there be any grounds,
the question of whether they are sufficient is entirely
for the judge at the
trial and this court cannot interfere with his
discretion.”
Counsel for the appellant submitted that the
learned trial judge in the case now under appeal had not dealt with the question
of costs
in accordance with the above statement of the law when he said in the
course of his judgment:
“Because each side has succeeded to some extent ..... there will be no
order as to costs.”
With respect, we are of opinion that the
learned trial judge failed to exercise his discretion judicially on the question
of costs
in accordance with the principle stated above. As Lord Alverstone said
on a matter involving an award of costs in Civil Service Co-operative
Society Limited v. General Steam Navigation Ltd (1903) 2 K.B. 756 at p.
766:
“If it appears that a judge has not exercised his discretion or has
decided upon grounds which are not open to him this court
can still deal with
his decision.”
For these reasons we conclude that costs
should have been awarded to the appellant. To avoid further reference to the
Supreme Court
we fix the amount to be allowed to the appellant in the Supreme
Court at $100 plus disbursements.
Accordingly, the appeal succeeds
in that the amount of appellant’s claim under the contract is increased
from $6,220 to $6,740;
less deductions for delay in completion of the contract,
$930, and faulty workmanship, $630; and appellant is entitled to some costs
in
the Supreme Court.
The cross appeal, is based on four grounds which
could be shortly set out under:
(a) That the learned trial judge, erred in law and in fact in holding that clause 12 of the contract had been waived by the respondent;
(b) That the delay in completion for which appellant was responsible should be calculated as at least 261 days and not 93, days;
(c) That the sum of $900 should not have been awarded for extra work done;
(d) That a considerably higher sum should have been allowed in respect of the
defective workmanship.
Ground (a) is based on clause 12 of the
written contract which reads:
“The Contractor shall not be entitled to do any extra or additional
work or to make any variation of the plans and specifications
without the
written consent of the Owner and Home Finance Company
Limited.”
It is common ground that the written consent of the
owner was not obtained. In our opinion, any additional work covered by Clause
12
must refer to additional work relating to the completing of the house and its
appurtenances, but cannot have reference to any
work lying outside the scope of
the contract The construction of the driveway was quite independent of what was
covered by the contract,
and accordingly there was no necessity for a written
agreement, in respect of that particular job.
In any event, even if
it could be held that the work came within the scope of the contract, that
particular clause could legally be
waived when a request was made by the party
concerned. It is clear law that compliance with a particular stipulation in a
contract
may be waived by agreement or conduct: 8 Halsbury,
3rd Ed., para 299. When, as here, one party makes a special
request to another party for a latter to do some work for him, and the
work is
performed, it would be contrary to all the principles of justice that the party
obtaining the benefit of the work should
be able to avoid liability for payment
for it on a technical objection such as that raised in this case. This ground
fails.
Ground (b) appears to be based on a contention that the
period of delay, should be calculated up to the time when all the items of
defective workmanship had been remedied. But these were matters which lay
outside the scope of the contract itself. The learned trial
judge found that the
figure claimed was “somewhat perplexing and unrealistic”. He held
that the delay should be calculated
up to the time when a certificate of
completion and permit to occupy was issued by, the appropriate municipal
authority. This was
on the 26thof March 1975. We are satisfied that
the learned trial judge was justified in his finding that the period of delay
for which the appellant
is liable in damages was correctly fixed as expiring on
that date, giving a total of 93 days in all.
No convincing argument
was put forward on ground (c). It was clearly established that the additional
work already referred to above
was carried out, by the appellant at the request
of the respondents and there is no suggestion that the amount allowed in respect
of that work is unreasonable.
On ground (d) the
argument of counsel for the respondents was directed to a consideration of the
conflicting evidence given in respect of the defective
workmanship by architect
Frederick Graham Walker for the appellant and joinery
manager,
Mahmood Khan, for the respondents. The witness Walker
deposed that it would cost between $350 and $450 to complete the house in
accordance
with the plans and specifications. The witness Khan estimated that
the total cost would amount to $5,456.70.The learned trial judge
found that Mr.
Walker who was the architect supervising the work on behalf of the mortgagee;
Home Finance Company Limited, was an
Independent and neutral witness. He also
stated that he found the evidence of witness Khan of little use. The
latter’s quotation
was prepared three years after the construction of the
dwelling house was completed. Moreover, it can hardly be said that he was
an
independent and neutral witness as in the course of his evidence he
said:
“I am hopeful to get contract to do job of rectifying
defect.”
The learned trial judge took the higher figure of
Mr. Walker’s assessment, $450, and added to that $180 to cover the poor
workmanship
in the driveway and the storm water drains, not included in Mr.
Walker’s report. Nothing in this could be held to be unfair
to the
respondents. It is well established that an appeal court will normally not
interfere with the findings of fact by a trial
judge who has seen and heard the
witnesses concerned, when he has based his findings on his opinion as to the
reliability of those
witnesses.
Accordingly, we can find no merit
in any of the grounds of the cross appeal which is therefore
dismissed.
In the result the appeal is allowed by increasing the
amount to which the appellant is entitled from $6,220 to the amount originally
claimed, $6,740, less $930 by way of damage for delay in completion of the
contract and $630 for defective workmanship. Accordingly,
there will be judgment
in favour of the appellant for $5,180 together with one set of costs to cover
this appeal and cross appeal,
the quantum of which to be fixed by the Registrar
of this Court. The appellant will also be allowed $100 plus disbursements by way
of costs in the Supreme Court.
Judgment for the
appellant.
-------
PacLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.paclii.org/fj/cases/FijiLawRp/1979/39.html