Wehrenberg v Bulivou [2014] FJMC 196; Civil Action 3 of 2010 (4 August 2014)

IN THE MAGISTRATES COURT OF FIJI
IN LABASA-NORTHERN DIVISION
CIVIL JURISDICTION


Civil. Action No. 03 of 2010


BETWEEN:


FRED WEHRENBERG,
of Nisusu Island, Savusavu
PLAINTIFF


AND


INOKE BULIVOU,
of Director of A.P Consultants Ltd,
Savusavu


BEFORE: RESIDENT MAGISTRATE, TOMASI BAINIVALU


COUNSEL: he Plaintiff- Appearing in person
Non-Appearance of the Defendant


DATE OF HEARING: 18th October, 2013
DATE OF RULING: 4th August, 2014


PLACE Labasa Magistrates Court


RULING

A. THE INTRODUCTION

1. This is one matter that has been pending for quite a while and the court records had detailed the various reasons to the same.

2. The Plaintiff, initially filed his writ of summon on the 07th June 2010; and several adjournments being made thereafter on the preliminary issues. And one of the issue at the preliminary stage of the proceedings, was the where about of the Defendants being unknown to the Plaintiff and even despite several attempts made by the Plaintiff the Defendant seems to be avoiding the Plaintiff and the court for that matter.

3. The court therefore at first formally proofed the Plaintiffs evidence on the 20th January, 2011 and judgment was delivered therefore in favor of the Plaintiff on the 18th February, 2011. Thereafter, motion and affidavit in support were filed by the Defendants Counsel then, Mr Naco to set aside the said judgment entered on 18/02/11.

4. And upon submissions filed by both the Plaintiff and the Defendant through his latter Counsel, the court ruled that the motion be granted and default judgment entered on the 18th February 2011 be set aside.

5. The High Court ruled on the appeal out of time issue on the 20th May 2013; where it further order that the matter be assigned an early hearing date in my court. I had therefore assigned the hearing on the earliest possible date, which is the 18th October 2013.

6. And again I must express my sincere apology to the Plaintiff for the long pending of this judgment and the inconvenience may hacve caused. And today I hereby deliver the judgment.

B. THE LAW

7. The laws and authorities are very clear in terms of the breach of contract and the non performance of any duty as agreed by parties to a contract.

8. The Plaintiff had furnished the court with some authorities, on which this court had decided to rely upon and again I must express my gratitude to the Plaintiff for furnishing them for ease of reference and I have reproduce them as follows, since majority of these authorities are persuasive to the common law principle in issue in this case.

9. The Defendant is the Director of A.P Consultants Ltd; Savusavu and the Plaintiff in his writ of summon is suing the said Defendant for breaching the contract due to his non - performance.

10. And following are some authorities that established the Plaintiffs legal standing in recovering what he claimed owed to him by the Defendant.

Procuring a breach of contract

And the court also noted the issue for liability of an agent as detailed on page 8 of the case of Wearsmart Textiles Ltd. v General Machinery Hire Ltd, Fiji Court of Appeal.

Breach of Duty of Care

Piercing the corporate veil

And also the court had cited the case of Intercept Corp v Calima Fin. LLC, that discusses the same principle.

Fiji Legislation

Commerce Commission Decree 2010

4(1) in this decree, unless the context otherwise requires -
"services" includes any rights (including rights in relation to, and interests in real or personal property) benefits, privileges, accommodation or facilities that are, or are to be provided, granted or conferred in trade or commerce and without limiting the generality of the foregoing includes the rights, benefits, privileges and facilities that are, or are to be provided, granted or conferred under

Accepting Payment without Being Able to Supply as Ordered

88 - (1) A person shall not, in trade or commerce, accept payment or other consideration for goods or services where, at the time of the acceptance -
(2) A person who contravenes this section shall be guilty of an offence.

Liability of Employer, Agent and Employee

"132 - (1) Any manager, agent or employee who in the course of his duties does or omits to do any act which if done or omitted to be done by his principal or employer would be an offence against any of the provisions of this decree or of any regulations or orders made there under shall himself be guilty of such offence, and shall be liable to the penalties provided therefore-under this decree or as the case may be, such regulations or orders.
133. Where any offence against this decree or against any regulations or orders made there under is committed by a company, firm or other. association of individuals, every person who at the time of the offence was a Director, Manager, Secretary or other similar officer of such company, firm or, association or who was at that time concerned in or purported to act, in the management of it, affairs, shall be severally liable in prosecution and punishment, in like manner as if he had himself committed the offence, unless he proves that the offence was committed without his consent and connivance and that he took all reasonable steps to prevent its commission."

C. THE APPLICATION /CLAIM

11. That the Plaintiff and his wife are the joint owners of one freehold island of Nisusu in the Savusavu district and are living on the island since July 2004. And the Defendant who is the Director of A.P Consultants Ltd; Savusavu and is sued for breach of contract due to his non - performance.

12. That on the 9th of February 2005 the plaintiff entered into a contract with the Defendant for the construction of his residence, a double story concrete house (9.5 x 9.5 x 5.5m) at Nisusu Island.

13. That the agreed contract price for the residence was $105,000,000. The contract price included the supply of materials to furnish labour, transport, supervision, tools, drawing and to obtain all approvals and Structural Engineers Certificate. It excluded however from the contract the electrical installation and the delivery and fitting of all aluminum windows and sliding doors which was the Plaintiffs responsibility to sub contract.

14. That the plaintiff made the first payment of $1,600.00 on 9.2.2005 and the Defendant instructed his architectural designer Mr. Maika to seek the necessary approvals.

15. That on 27.5.2005 the defendant visited the plaintiff at Nisusu Island and showed the Plaintiff a letter from the Local Authority given building permission for the residence.

16. That the defendant confirmed to the plaintiff that he is ready to start the construction, but requested that the 2nd and 3rd payment be increased to $30,000.00 each instead of $22,700.00 each as stipulated in the contract and therefore the 4th payment should be reduced accordingly by $14,600.00 to a total of $28,400.00. The Plaintiff reluctantly agreed and made the 2nd payment of $30,000.00 on 27/5/2005 and soon thereafter the Defendants workers began the construction with completion scheduled to be in 25 weeks.

17. That after the completion of the foundation and concrete floor the Defendant dismissed the supervisor Mr. Abdul in August 2005, reason being that he was too expensive. The plaintiff noticed with great concern that the workmanship and efficiency of the workers deteoriated dramatically, because there was no proper supervision on site. That the

18. Plaintiff raised his concern about this matter on numerous occasion but the Defendant ignored it and the Plaintiff was just left to deal with the impossible situation on site.

19. That on 26.09.2005 the Defendant who had gone to Suva asked therefore his Manager Mr. Usaia Jeke for the 3rd payment of $30,000.00 from the plaintiff despite the fact that the ground floor was far from complete. The Plaintiff raised the following concerns:-

(a) That the ground floor was far from complete because the concrete ceiling was missing.
(b) That the workmanship and efficiency of the workers was bad and that the Plaintiff had to be on site and supervise and give technical advice nearly every day.
(c) That the Plaintiff had already made the 2nd payment higher by $7,300.00 and that he was surprised where all his funds had gone.

That the Manager promised to improve the situation and for the sake of making progress and make this project work, the Plaintiff reluctantly agreed to make five part payments between 26.09.2005 and 2.3.2006 totaling $29,500.00

20. That on 4.9.2006 after the Plaintiff had made three payments totaling $61,325.00 the Defendant suddenly withdrew all his workers from the construction site and told his Manager Mr. Jeke to advise the Plaintiff that there is no money to carry on.

21. That the Plaintiff was shocked and outraged because;

a) The Plaintiff had performed all his obligations under the contract and in fact had already paid $14,325.00 more than required by contract.
b) The 3rd payment which the Plaintiff had made was for the construction of the 1st floor but the Defendant had failed to complete the 1st floor because the concrete roof, facia including some interior walls had not even been constructed yet and the Defendant had already run out of the Plaintiffs funds totaling $61,325.00
c) The time to carry out the whole job had already gone far past the 25 weeks.

22. That the Plaintiff tried to contact the Defendant who had disappeared to Suva, without success. Numerous attempts were made by the Plaintiff to contact the Defendant but to no avail as the Defendant closed his business in Savusavu and moved to Viti Levu in 2006. The Defendant has been avoiding the Plaintiff by not turning up to appointments, changing and diverting his mobile phone numbers, not replying to letters and constantly changing his residence.

23. The Plaintiff had to spend a total of $131,646.91 for the construction of his residence, as detailed below:

a) Payment made by the Plaintiff to the Defendant Between 9.2.2005 and 4.9.2006 was $61,325.00;
b) For the purchase of materials by the plaintiff between 2006 and May 2008 due to the Defendants mismanagement of $32,961.33
Funds and breach of contract.
c) For the purpose of materials and the hire of trades-men By the Plaintiff between June 2008 and December 2009:- $37, 360.58
To complete the said residence due to the breach of contract by the Defendant.
Total $131,646.91

24. That as a direct result of the said breach of contract by the Defendant the Plaintiff had to pay $31, 546.91 more than the contract price agreed upon as shown below:

a) Total cost to construct and complete residence
:-
$131, 646.91
b) Contract price
:-
$105,000.000
c) Adjustment to contract price as per clause 6 of contract.
175 sqm of floor tiles at $55.00 per square meter was stipulated In contract but plaintiff selected floor tiles at $27.00 per square meter
A saving of
:-
$100,100.00
Extra Cost of
:-
$31, 546.91

25. Wherefore the Plaintiff Claims as follows:-

a) Special damages in the sum of $30.826.91
b) General Damages
c) Damages for distress and mental anguish caused to Plaintiff and wife
d) Damages of the 4 years delay until the construction of residence was finally completed
e) Interest on damages
f) Cost of this action, plus costs of $2000.00 for bailiff, motions, advertisements etc to locate the Defedant who was evading the litigation process
g) Such further and/or other relief as this Honorable Court may deem just and expedient

D THE EVIDENCE

26. I must express my sincere appreciation to the Plaintiff for detailing the full transactions and dealings between himself and the Defendant via Affidavit of Evidence in chief together with the bundle of exhibits confirming every transaction made, for ease of the courts reference and its perusal leading to the conclution of its final determinations.

27. I therefore had reproduced all the relevant evidence in chief as follows:-

AFFIDAVIT OF FRED WEHRENBERG

"I, FRED WEHRENBERG of Nisusu Island, Savusavu, Electrical Engineer make oath and say as follows:

1. THAT I am the plaintiff herein and make this affidavit in support of my common law suit against the defendant Inoke Bulivou for his tortious acts of negligence, personal carelessness, breach of duty of care, misappropriation of my funds and non-appearance which resulted in the breach of contract.
2. THAT in 2002 Mr Arun Prasad the former Director of A.P Consultants Ltd. In Labasa surveyed the freehold island of Nisusu and filed the necessary plans at the Titles Office for purposed that I could purchase the island and obtain Certificate of Titles. Mr Prasad carried out his work to my satisfaction.
3. THAT in late 2004 I was looking for a drafting office in Savusavu to computerise the detail sketches of my proposed double story residence for approval and tendering process, when I noticed a signboard of A.P Consultant Ltd. On the main street town. As I had made good experience with A.P Consultant Ltd. Labasa, I enquired at A.P Consultant's Office in Savusavu
4. THAT I met the defendant Mr Inoke Bulivou who was the director of A.P Consultants Ltd. And I asked him whether he can computerise my sketches for the double story residence.
MrBulivou was interested and he advised me that he is in the process of employing an architectural designer, as the wants to expand his survey business into the building industry.
5. THAT in January 2005 defendant Inoke Bulivou introduced me to his architectural designer Mr Maika and during detailed discussions the defendant was very keen and persuasive to take on the complete project (design, approval, construction and supervision, incl. completion certificate and engineering certificate) of the double story building.
6. THAT between January 2005 and 9th of February 2005 I met with defendant together with his architectural designer on numerous occasions in his office to come to an agreement on the contract price, which was based on the bill of quantities and the detail drawings produced by Mr Maika after making inquiries with the Local Authority and a Civil engineer. Mr Bulivou was always present in those meetings and was in charge of the negotiations. Mr Bulivou made site visits to inspect the building site and to establish the method of transportation of building materials from the mainland to the island of Nisusu and Mr Bulivou decided that he would get a boat.
7. THAT after obtaining and considering the quotes from other building companies I and my wife entered on 9th of February 2005 into a contract with the defendant Inoke Bulivou of A.P Consultant Ltd. For construction of my residence, a double story concrete house (9.5 x 9.5 x 5.5m) at Nisusu Island. The agreed contract price for the residence was $105,000.00.
The contract price included the purchasing and supply of materials, labour, transport, supervision, tools, drawings and to obtain all approvals, incl. structural engineer certificate.
That however, the contract excluded the electrical installation and the delivery and fitting of all aluminum windows and sliding doors, which was my responsibility to sub-contract. (Refer paragraph 10 and 11 of contracts, Annex P1)
8. THAT the said contract and the price, including the payment schedule were worked out only between Inoke Bulivou, my wife and me at Mr Bulivou's office. The contract was signed by the defendant Inoke Bulivou, my wife and I. According to the paragraph 17 and 18 of the contract the total time to carry out the job was to be 25 weeks, with the following payment schedule:
9. THAT because the contract included not only the construction of the double story building, but also the drawings, approvals by the Nasavusavu Local Authority and the structural engineers certificate, it was agreed that any variation to the structure (i.e. concrete block size and steel thickness) made as a result of miscalculation by the defendant and Mr Maika would be without any additional cost to me.
Paragraph 1 of the Contract states as follows:
10. THAT I never made any changes to the overall size of the building, the number and size of rooms, doors and windows.
The changes to concrete block size and amount and size of steel were made by the structural engineer, hired by defendant Inoke Bulivou, as a result of a mistake made by his employee Mr Maika.
In paragraph 3 (b) of the defendant's statement of defence filed on 2.4.2012 this fact is admitted:
The floor plans made by Mr Maika in January 2005 (annex "P2") and the plans approved by the structural engineer (annex "P3) a few months later are annexed herewith. ANNEX "P2 + P3"
11. THAT the defendant Inoke Bulivou did not mention any of the changes, nor did he ask me and my wife for an increase of the agreed contract price, because he was aware of paragraph 1 of the contract.
12. THAT after the signing of the contract on 9.2.2005 I gave a cheque of $1,600.00 as first payment to Inoke Bulivou, who then instructed Mr Maika to seek the necessary approvals. ANNEX "P4"
13. THAT on 27.5.2005 Inoke Bulivou visited me and my wife at Nisusu Island and showed me letter of the Nasavusavu Local Authority giving building permission for my residence.
14. THAT Inoke Bulivou confirmed during this visit that he is ready to start the construction, but requested that the second and third payment be increased to $30, 000.00 each instead of $22,700.00 each as stipulated in the contract and that therefore the fourth payment should be reduced accordingly by $14,600.00 to a total of $28,400.00. The contract price of $105,000.00 would remain the same.
I did not like Mr Bulivou's request, but because he was very persuasive and I had been told that he was a pastor of a church, I reluctantly gave him a cheque of $30,000.00 on 27.5.2005.
That Inoke Bulivou did definitely not ask to increase the total contract price of $105,000.00 and neither my wife nor I would have agreed to it.
It was mutually agreed on 27.5.2005 that the increased amount of $7, 000.00 for each (the 2nd and 3rd progress payment) to be deducted from the 4th progress payment, as stated in paragraph 1. (e) 1. Of my letter dated 11.5.07 to the defendant: ANNEX "P6"
15. THAT in June 2005 Inoke Bulivou came to our island with his survey equipment to determine the exact position of the foundation of the double story building. Soon thereafter the construction team, led by Mr Abdul arrived on site and the work commenced.
16. THAT soon, thereafter Inoke Bulivou took the following careless action:
17. THAT as a result of Inoke Bulivou's carelessness and breach of duty of care I noticed with great concern the following:
I raised my concern about the above situation with the defendant Inoke Bulivou on many occasions verbally and later also writing, but he ignored it and I was just left alone to deal with the impossible situations on site.
In my letter dated 11.5.2007 to the defendant Inoke Bulivou I wrote the following:
I raised my utmost concern about the following:
ANNEX "P6"
18. THAT by September 2005 the defendant Inoke Bulivou had disappeared to Suva and his whereabouts was unknown.
However, Inoke Bulivou gave instructions to his manager Usaia Jeke, a surveyor, who was not versed with the project, to collect on 26.9.2005 the 3rd payment of $30,000 from me, despite the fact that the ground floor was far from complete.
19. THAT I raised the following concerns to the Manager Usaia Jeke:
20. THAT Usaia Jeke promised during his visit on 26.9.2005 to improve the situation and during intense interrogation he admitted the following:
That I refused to make any payment for a bridge loan, but for the sake of making progress and to make project work, I reluctantly agreed to make progress payments.
21. THAT from 26.9.2005 I made the following progress payments totalling $29,500.00 until the concrete ceiling (3rd stage) was completed on 2.3.05:
a) 1st progress payment.
26.09.05
470
$3,000.00
b) 2nd progress payment
18.10.05
490
$12,500.00
c) 3rd progress payment
31.10.05
494
$10,000.00
d) 4th progress payment
16.12.05
515
$2,500.00
e) 5th progress payment
02.03.06
557
$1,500.00



$29,500.00
ANNEX "P4"
22. THAT however, on 4.9.2006, after I had made 3 payments totalling to $61,325.00; Inoke Bulivou suddenly withdrew all his workers from the construction site and told his manager Mr Jeke to advise me that there is no money to carry on.
23. THAT I was shocked and outraged because:
24. THAT I made numerous attempts to contact the defendant Inoke Bulivou who had disappeared to Suva to no avail. Inoke avoided me by not turning up to appointment, changing and diverting his mobile phone numbers, not replying to my letters and constantly changing his address.
25. THAT in consequence I advised the defendant's manager Mr Jeke verbally and in writing that if they fail to resume the construction I would take legal action. In my latter dated 7.9.2006 I state as follows:
If you fail to resume the construction by Monday the 11th of September 2006, we have no other option but to take the matter to Court on breach of contract.
26. THAT on 8.9.2006 the defendant's manager Mr Jeke came for a meeting to my island. I advised him that unless the construction of the residence is continuing, I would take legal actions.

Mr Jeke then admitted the following:

a) That the defendant Inoke Bulivou had withdrawn large amounts from the company's bank account, and had misused my funds for purpose other then what they were intended for.
b) That he (Jeke) had no access to the company's bank account. The only one who had access to the bank account was the defendant Inoke Bulivou.
27. THAT the defendant's manager Mr Jeke then agreed on 8.9.2006 to carry on the construction work, if I would agree to pay for the materials only. The cost for the materials would be deducted from the contract price.
Mr Jeke would be responsible for the employment of the workers and he would also pay their wages, from income he would make from his surveying.
That due to the difficulties circumstances, whereby the defendant had disappeared and misused my funds and could not be located, I agreed to the manager's proposal.
28. THAT on 11.9.2006 a new team of workers carried on the construction work, which progressed very slowly.
That I purchased the necessary materials and also had to conduct the construction supervision, which was very challenging and difficult at times, because the defendant's manager Mr Jeke did not pay the workers regularly and most of the workers were unskilled.
29. THAT on 1.5.2007 at about 1.30pm I caught the defendant Inoke Bulivou who was on a brief visit at his office in Savusavu and I had a meeting with him and his manager Mr Jeke.
In this meeting I stated my concerns as shown in paragraph 1 (a) to (h) of my letter dated 11.5.2007.
Finally, after 2 hours the following points were agreed upon, as stated in paragraph 1 (a) to (e) of the same letter to the defendant Inoke Bulivou:
30. THAT unfortunately all promises made by the defendant Inoke Bulivou on 1.5.2007 have been false and matters even got worse, as shown in paragraph 3 (a) to (e) of my letter dated 11.5.2007.
31. THAT on 23.5.2008, after I had purchased materials valued at $32,241.33, which I selected in accordance with the contract and building standards, the construction work stopped because the workers had not been paid by the defendant nor his manager Mr Jeke. According to the contract the building should have been completed after 25 weeks but after 150 weeks the residence was still far from complete. A photo of the building as it was May 2008 is annexed,
32. THAT the purchase of the materials involved getting quotations, making many phone calls and numerous trips from Savusavu to Suva, selecting the materials and organize their shipment to Savusavu and to the building site.
A list of the materials purchased by me between 2006 and May 2008 is annexed herewith.
33. THAT on 10.7.2008 my wife delivered a letter to the secretary of A.P Consultant Ltd, urging the defendant Inoke Bulivou and his manager to resume the construction work immediately and to complete the project until 30.9.2008, or legal action would be taken.
That I received no response from the defendant Inoke Bulivou, but the manager removed A.P Consultant's outside-signboard and cleared out the office in mid August 2008.
34. THAT I made a complaint against the defendant Inoke Bulivou with the Fiji Independent Commission against Corruption for the defendant's fraudulent conduct and also sought their assistance in locating the defendant. A letter from FICAC dated 12.9.2008 is annexed.
35. THAT due to the breach of contract by defendant, I had to hire tradesman, plaster men, tile layer, plumber etc and had to purchase all materials necessary to complete my residence..
The finishing work included:
36. THAT all the finishing work and all materials I purchased were in accordance with the contract and the building standards. There were on extras.
I had to spend an additional $37,360.58 for materials and labour for workers, including for my own labour of 2005 hours to complete the residence.
A photo of the completed residence is annexed as "P14".
A list of the materials purchased by me between June 2008 and December 2009 is annexed herewith.
ANNEX "P10"
37. THAT I had to spend a total of $130,926.91 for the construction of my residence as detailed below.
38. THAT as a direct result of the said tortious acts and breach of contract by the defendant Inoke Bulivou, I had to pay $30,826.91 more than the contract price agreed upon as detailed below:
a.
total cost to construct and complete residence
$130,926.91
b.
Contract price (VIP)
$105,000.00
c.
Adjustment to contract price as per paragraph 6 of contract l75 sqm of floor tiles at $55.00 per sqm was stipulated in the contract, but I selected floor tiles at lesser price of $27.00 per sqm, a saving of $4, 900.

Adjusted contract price $100,100.00
$100,100.00

Extra Cost of
$30,826.91
39. THAT on 29.12.2009 I wrote a registered letter to A.P Consultants Ltd, to both Savusavu and Labasa, as I did not know the whereabouts of the defendant Inoke Bulivou, I detailed the extra cost due to the defendant's breach of contract and ask for payments by 31.1.210, or I would take legal action. ANNEX "P11"
40. THAT while I, FICAC and my bailiff tried to locate the defendant Inoke Bulivou I became aware of the following:
41. THAT this civil suit is a common law claim against the defendant, holding him personally liable for procuring a breach of contract and for breach of duty of care. That the defendant Inoke Bulivou was not only the director and shareholder of AP Consultants Ltd, but he was also the mind and will of his company and personally exercised full control over the building project as shown below:
Furthermore, the defendant has been evading me and the litigation process and he is now misusing his company as a device or facade to conceal his wrong doings.
42. THAT I am aware that the Courts in Fiji, England, Australia, New Zealand and USA have ruled in the past in regard to the director's liability as follows:
43. THAT as a result of breach of contract and breach of duty of care by the defendant Inoke Bulivou, I suffered special and general damages and costs:
44. THAT I pray to this Honourable Courts for reasons aforesaid that compensation be granted for loss and damages I have suffered.

28. The court also in this judgment had considered the Plaintiffs wife namely WALBURGA WEHRENBERGs', affidavit of evidence in chief and I do not wish too reproduce the same as the court record has it. The Plaintiffs wife was the third party to the contract, which was signed by the defendant Inoke Bulivou, the plaintiff and herself on 9.2.2005.

E. THE DETERMINATION AND CONCLUSION

29. The Defendants obvious and unacceptable attitude towards the full proceedings when the matter was called before my court had deemed to be his indication on full admissions to the claim, by avoiding every court dates and even had failed to oppose the claim on the hearing date. At one stage, I have noted that the former Counsel, Mr Naco had lost touch in getting instruction from his client, that had resulted of him being withdrawn from representing the Defendant anymore.

27. I have also noted and perused every documents tendered in court as part of the Plaintiffs'; evidence and I am satisfied that there was indeed a breach of contract due to the Defendants non-performance of his duties and he had had failed to honor his part of the bargain as per contract executed by all the parties on the 09th February, 2005.

28. .In considering all the above detailed evidence in chief, the authorities and principles reference to the issue of breach of contract, it is clear to this court and I am satisfied that the Defendant entered into a contract for the construction of the Plaintiff's residence and such there was a contract price of $105,000.00, and the total cost to construct and complete the said residence was $130,926.91; and due to the Defendants non-performance and failing to complete his obligations, the Plaintiff had to pay an extra $30,826.91 together with the cost of the $2000.00 as bailiff costs.

29. I have also noted and made to accept that the Plaintiff had suffered loss in terms of transportations, accomodations etc and must considered with some general damages caused upon him whilst being coming to court for the past four years.

30. The Court therefore Orders as follows:

a. The Defendant shall pay to the Plaintiff the total sum of $30,826.91 being the refund of the extra cost he incurred to complete the construction of his residence.
b. The Defendants shall further pay the Plaintiff the sum of $2000.00 being costs for Bailiff, motions and advertisements.
c. The Defendants shall further pay the Plaintiff the sum of $6000.00 assessed by the court as general damages and for the delay of the proceedings caused by the Defendant.
d. Therefore the total sum the Defendants shall pay the Plaintiff is $38,826.91 being the total judgment sum.

Dated at LABASA this 4th day of August, 2014.


Tomasi Bainivalu (Mr)
Resident Magistrate


LABASA / SAVUSAVU